Kanpur ( Metro Rail News): Another milestone has been achieved for Kanpur Metro phase 1 as Afcons-Sam India Consortium’s TBM Vidyarthi recorded its second breakthrough at Transport Nagar Station of Line 1 under Package KNPCC-06.
This is the overall 4th breakthrough out of 8 breakthroughs planned under Package KNPCC-06.


TBM Vidyarthi’s Journey
TBM S-639B, nicknamed Vidyarthi, started its journey in December 2023 as the fourth TBM deployed for the construction of downline underground tunnels on Line 1 spanning 23.78 Km from IIT Kanpur to Naubasta.
| Current Assignment | Transport Nagar Ramp -Transport Nagar Station | 331 m | November 2024 |
| First Assignment | Kanpur Central Station- Nayaganj Station. | 1250 m | June 2024 |
KNPCC- 06 Package
Afcon Sam India Consortium grabbed package KNPCC-06 spanning 4.65 km approx from UPMRC at Rs. 1087.76 cores with a 36-month deadline.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
The scope of work under this package includes the construction of underground tunnels at 3 stations from Nayaganj Station to Transport Nagar Ramp for Line 1 of Kanpur Metro.
Stations:
- Kanpur Central
- Jhakarkatti
- Transport Nagar
Future Prospects:
TBM Vidyarthi will be dragged from Transport Nagar Station towards Jhakarkatti for its third and final breakthrough for Package KNPCC-06.
Project Overview