YFC Projects – BBG JV Submit Bid for Package C-09 of Nagpur Metro Phase 2

YFC Projects – BBG JV Submit Bid for Package C-09 of Nagpur Metro Phase 2
Nagpur Metro

Nagpur (Metro Rail News): On 12 November, Maha Metro opened the bids for package C-09 of the 43.8 km Nagpur Metro phase 2 project, revealing YFC Projects – BBG Infrastructure JV as the sole bidder for the contract.

Nagpur Metro Phase 2 map

Scope of Nagpur Metro Package C-09

The appointed contractor for this contract will be responsible for the construction of 8 elevated stations on Reach 1A, which is an extension of the Orange Line. The 8 stations are:

  • Ashokvan
  • Dongargaon
  • Mohgaon
  • Meghdoot CIDCO
  • Butibori Police Station
  • MHADA Colony 
  • MIDC KEC and 
  • MIDC ESR 

Bidding Process 

Maha Metro initiated the bidding for contract C-09 in April 2024 with an estimated cost of Rs. 258 crore and a 2.5-year deadline.

Funding Mechanism

Package C-09 will utilise funding from a $ 200 loan that was sanctioned by the Asian Development Bank in July 2024 for Nagpur Metro Phase 2.

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

The viaduct that will connect the stations on this package will be constructed by GR Infraprojects (GRIL) under package C-02, which is worth Rs. 903.53 crore.

The Process Ahead

It is likely that the bid submitted by YFC-BBG JV will undergo technical evaluation. Following the successful technical evaluation Maha Metro will reveal the financial bid for the contract.

Enia Design became the lowest bidder for the DDC-03 contract, which includes the development of various designs for all 8 stations.