Kanpur (Metro Rail News): On November 11, Ceigall India successfully launched the first
of 184 U-girders for Package KNPCC-12 on Kanpur Metro’s Line-2. The Line 2 spans 8.38
kilometres and connects Agriculture University to Barra-8 via eight stations.
This milestone was achieved in the ramp area near the Agriculture Metro station and depot,
which is currently under construction under Package KNPCC-14.

KanpurMetro Line2 UGirder2
Kanpur metro
u Grider

Package KNPCC-12 Of Kanpur Metro

Ceigall India was awarded package KNPCC-12 from UPMRC at Rs. 427.11 crore in March
2024 with a 30-month deadline.
The scope of work under this package includes two separate elevated sections on either side
of the underground package KNPCC-1, which connects the Agriculture Depot to the Double
Pullia Ramp.

54137481912 72af52c632 o


The southern portion of KNPCC-12 features a 3.75 km elevated section extending from
Double Pullia Ramp to Barra 8 with 4 elevated stations at Vijay Nagar Chauraha, Shastri
Chowk, Barra-7 Station and Barra-8. Additionally, to the north, beyond the Rawatpur
Interchange Station, a shorter viaduct spanning 557.8 meters will be constructed, including an
elevated station at Agriculture University adjacent to Line-2’s Agriculture University Depot.

Guide

Kanpur Metro: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here