KANPUR (Metro Rail News): Kanpur Metro’s Corridor 2 has reached another construction milestone with the casting of its first scissor crossover near the Vijay Nagar Chauraha elevated station. At the same time, installation and testing of lifts and escalators are progressing at three underground stations, as civil construction and systems work move forward in parallel.
The Uttar Pradesh Metro Rail Corporation (UPMRC) is developing Corridor 2 between Agriculture University and Barra-8. The 8.60-km corridor will have five elevated and three underground stations.
First scissor crossover completed near Vijay Nagar
UPMRC has completed the casting of the first scissor crossover on the viaduct near Vijay Nagar Chauraha elevated station of Kanpur Metro. The crossover will allow trains to switch between tracks, providing operational flexibility for train movements. The corridor will have three scissor crossovers and two other crossovers to support track-changing operations.

These structures will form part of the track infrastructure required to manage train movements and service operations along the corridor.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
Lift and escalator installation underway at underground stations
Work on passenger facilities is progressing at Rawatpur, Kakadeo and Double Puliya underground stations. These stations form part of Kanpur Metro Corridor’s 2 4.10-km underground section. A total of 12 escalators and seven lifts are being installed across the three stations. Installation and testing are currently underway.

The elevated section will also receive 18 escalators and 18 lifts. All the lifts and escalators are being manufactured in Chennai under the Centre’s Make in India initiative.
Energy-efficient systems and passenger safety features
The equipment includes features designed to reduce power consumption and improve passenger safety. Smart escalators automatically stop when they remain unused for a specified period, helping reduce electricity consumption. They also include:
- Three emergency stop buttons.
- Automatic announcements to provide safety instructions to passengers.
Lifts use regenerative braking technology, which recovers energy generated during braking and makes it available for reuse. These facilities are expected to improve access for daily commuters, senior citizens and passengers with disabilities.
Kanpur Metro Corridor 2: Civil construction and systems work progress together
UPMRC Managing Director Sushil Kumar said civil construction and systems installation are progressing simultaneously on Kanpur Metro’s Corridor 2. The parallel execution approach is intended to advance station infrastructure and passenger facilities together. The corridor will connect Agriculture University with Barra-8 through five elevated and three underground stations. Its 4.10-km underground section includes Rawatpur, Kakadeo and Double Puliya.
The first scissor crossover and progress on lifts and escalators mark advances in both track infrastructure and station systems. Once completed, these facilities will support train operations and provide more accessible passenger movement across Kanpur Metro’s second corridor.