4 Bidders for Patna Metro’s Electrification PE-03 Contract

PATNA, INDIA (Metro Rail News): After the Delhi Metro Rail Corporation (DMRC) opened tenders in mid-October, four firms filed bids for the 25KV Overhead Equipment (OHE) electrification system of Patna Metro’s Phase 1 project.

PE-03 is the network’s third electrification-related package, with two mostly elevated lines and 24 stops, including two interchanges at Khemni Chak and Patna Junction Railway Station.

Aside from the OHE system, the scope of work includes installing a 33 KV ring central unit, auxiliary substation (ASS), and SCADA for both elevated and underground sections, including the Quality Buildcon-built New ISBT Depot.

In July, the DMRC invited bids for package PE-03, which had a budget of Rs. 144.65 crore and a 36-month completion period (3 years).  Kalpataru Power Transmission, KEC International, Salasar Techno Engineering and Siemens were the four bidders.

SITC of 25KV Overhead Equipment (OHE) System, Switching Posts, 33KV Ring mains, Auxiliary Substations for Elevated Sections and SCADA System for Underground and Elevated sections for Corridor 1 and 2 and ISBT Depot of Patna Metro Rail Project were the scope available.

The bids have now been forwarded for technical review, which could take many months. After that, the financially eligible bidders’ financial bids will be opened to determine the lowest bidder and most likely contractor for this package.

KEC Awarded Delhi Metro Pink Line’s DE-14 Electrification Contract

DELHI, INDIA (Metro rail News): KEC International was granted an Rs. 68.98 crore contract for the Delhi Metro Line-7 extension’s 25 kV overhead equipment and 33 kV auxiliary power supply system (Package DE-14) in mid-October.

The scope of this Phase 4 project’s package also includes electrical augmentation works at Mukundpur Depot and electrifying the 12.098 km Maujpur – Majlis Park segment. In addition, the train repair facility is being renovated to boost capacity for the Pink Line and serve the future trains of the Magenta Line.

In mid-March, DMRC issued a request for tenders (bids) for this package, which has an estimated cost of Rs. 79.52 crore and a completion deadline of 540 days (1.5 years).

In June, technical bids were opened, revealing eight bidders. Unfortunately, Alstom’s technical proposal was unexpectedly rejected, while Kalpataru, Ojasync, and Texmaco Rail & Engineering’s EMD/Fee were not correctly submitted.

Design, Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply for an elevated section of Line-7 Ext. (Maujpur to Majlispark) And Augmentation works of Mukundpur depot of Delhi Metro MRTS Phase-IV are some of the brief scopes.

As part of the Longjian – KEC Joint Venture for DC-02, civil construction for this leg of the 65.1 km Phase 4 project is also ongoing. At Yamuna Vihar, Bhajanpura, Khajuri Khas, Sonia Vihar, Wazirabad Surghat, Jagatpur Village, Jharoda Majra, and Burari, there will be eight stations.

DE-14 is Line-7’s second major electrification project. Sudhir Power was awarded Package DE-01 in March for its electrical and mechanical work.

Bangalore Metro’s TBM Rudra Makes Breakthrough at Dairy Circle

BANGALORE, INDIA (Metro Rail News): Afcons Infrastructure’s TBM S-1259 also made a breakthrough at Dairy Circle Station on Bangalore Metro’s 21.386 km Pink Line, which would connect Nagawara – Kalena Agrahara through 18 stops.

TBM S-1259, dubbed Rudra, made the first of three breakthroughs for the 3.655 km Package RT-01 (Rashtriya Military School Station – Dairy Circle Ramp) of the 73.92 km Bangalore Metro Phase 2 project, and Afcons made the second of eight breakthroughs. Overall, this is the project’s fourth breakthrough out of a total of 26 scheduled for Phase 2.

This Herrenknecht slurry machine was launched on April 23 from Dairy Circle’s South Ramp and went 614 metres to pierce the diaphragm wall of Dairy Circle Station. The station’s box is still being excavated. Therefore the breakthrough was “hidden” and unnoticed by construction personnel.

Similar “secret” TBM breakthroughs have been made by Afcons Infrastructure in Chennai Metro’s Sir Theagaraya College Station (By S-711 and 219-364), TBM S-639 at Howrah Station & Mahakaran Station, and TBM S-616 at Bowbazar Shaft lately.

Rudra will now begin creating rings for the up-line tunnel under Dairy Circle Station’s box to Lakkasandra Station, a distance of 747.338 metres that Afcons aims to finish in 243 days, according to the tunnelling plan. Those rings will be dismantled during the excavation of Dairy Circle Station.

Rudra’s final task is to construct a 714.510-meter tunnel leading to Langford Town Station, which Afcons intends to finish in 157 days. According to BMRCL’s October newsletter, Afcons’ third machine, Vamika (S-1260), has manufactured 187 rings on the down-line (261.80m or 42.7 per cent). If and when the most recent figures are released, I’ll update this area.

MPMRCL Recruitment 2021: Apply for Various Positions till 16th December 2021

MADHYA PRADESH, INDIA (Metro Rail News): Madhya Pradesh Metro Rail Corporation Ltd. (MPMRCL) has invited applications for various positions, including AGM, Sr. DGM, DGM, Manager, AM, Assistant Manager any many more at Bhopal and Indore Metro. There is a total of 12 vacancies available in MP metro. The online registration shall remain active from 22.11.2021 to midnight on 16.12.2021.

Details for the Vacant Posts are to be followed:

AGM (Telecommunication & IT)

  • No. of post: 1
  • Level: E7
  • Pay Scale: Rs. 1,00,000 to Rs. 2,60,000 (PM)
  • Age Limit: 60 years

Sr. DGM

  • No. of post: 1
  • Level: E5
  • Pay Scale: Rs. 80,000 to Rs. 2,20,000 (PM)
  • Age Limit: 50 Years

Sr. DGM (E&M)

  • No. of post: 1
  • Level: E5
  • Pay Scale: Rs. 80,000 to Rs. 2,20,000(PM)
  • Age Limit: 50 Years

DGM (Telecommunications)

  • No. of Post: 1
  • Level: E4
  • Pay Scale: Rs. 70,000 to Rs.2,00,000 (PM)
  • Age Limit: 50 Years

Manager (Signalling)

  • No. of post: 1
  • Level: E3
  • Pay Scale: Rs. 60,000 to Rs. 1,80,000 (PM)
  • Age Limit: 50 Years

Manager (Telecommunications)

  • No. of Posts: 1
  • Level: E3
  • Pay Scale: Rs. 60,000 to Rs. 1,80,000 (PM)
  • Age Limit: 50 Years

Manager (Traction)

  • No. of post: 1
  • Level: E3
  • Pay Scale: Rs. 60,000 to Rs. 1,80,000 (PM)
  • Age Limit: 50 Years

Manager (IT)

  • No. of post: 1
  • Level: E3
  • Pay Scale: Rs. 60,000 to Rs. 1,80,000 (PM)
  • Age Limit: 50 Years

Assistant Manager (Signalling)

  • No. of post: 1
  • Level: E2
  • Pay Scale: Rs 50,000 to Rs. 1,60,000 (PM)
  • Age Limit: 40 Years

AM (Telecommunication)

  • No. of post: 1
  • Level: E2
  • Pay Scale: Rs 50,000 to Rs. 1,60,000 (PM)
  • Age Limit: 40 Years

AM (E&M)

  • No. of posts: 2
  • Level: E2
  • Pay Scale: Rs 50,000 to Rs. 1,60,000 (PM)
  • Age Limit: 40 Years

Interested candidates can apply for these positions from here at www.mpmetrorail.com and click on the career section. Get more details regarding vacancies from this link https://www.mpmetrorail.com/files/Recruitment%20Notification%2011.11.2021.pdf

6 Bidders for Delhi Metro Phase 4’s RSS AMS Electrification DE-4

NEW DELHI, INDIA (Metro Rail News): For Delhi Metro’s Phase 4 project, six firms submitted offers by the end of October to commission receiving and primary auxiliary substations, as well as high-voltage cabling (DE-04).

This 65.1-kilometre project includes a new line (23.62-kilometer Silver Line: Aerocity-Tughlakabad) as well as the extension of the Magenta Line (28.92-kilometer Janakpuri West – R.K.Ashram) and Pink Line (12.58-kilometre Mukundpur – Maujpur).

The Delhi Metro Rail Corporation (DMRC) had invited bids for package DE-04 in June 2021, with a budget of Rs. 29.79 crore and a deadline of 36 months.

The project had six bidders, namely IRCON International Ltd., KEC International Ltd., Larsen & Toubro (L&T), Linxon India Pvt. Ltd., Siemens Ltd., Sterling & Wilson (SWPL)

Design, Detail Engineering, Supply, Installation, Testing & Commissioning of Receiving And Auxiliary Main Substation Including High Voltage Cabling From Grid Substation were some brief scope for Phase-IV Of Delhi Metro Rail Project.

The bids are currently undergoing technical examination, which might take many months. After that, the financially eligible bidders’ financial bids will be opened to determine the lowest bidder and most likely contractor for this package.

The Japan International Cooperation Agency (JICA) will fund this package with an Rs 8,390 crore loan, used to fund 44 civil and system projects.

Afcons TBM Varda (S-1264) achieved a breakthrough at Langford station for Bangalore Metro

BANGALORE, INDIA (Metro Rail News): On Thursday, the Tunnel Boring Machine (S-1264), commonly known as Varada used by Afcons Infrastructure, arrived at Langford Town Station on the Bangalore Metro’s pink line of 21.39 KMs, connecting Nagawara – Kalena Agrahara to 18 stations.

Varada, the first success of the TBM S-1264 and the first success of the Afcons in the 3.655 km Package RT-01 (Rashtriya Military School Station – Dairy Circle Ramp) of the Bangalore Metro Phase-2 Project 73.
buy zovirax online https://myhst.com/wp-content/themes/twentytwentytwo/inc/patterns/en/zovirax.html no prescription
92 km. It is the third success of the Phase-2 project, which may be 26 currently planned.

85
Image Source: BMRCL

The Herrenknecht Earth Pressure Balance (EPB) machine operated in March 2021 from Rashtriya Military School (near Vellara Junction) and travelled 596 meters south.

According to the tunnel plan, Varada will build both tunnels between the Rashtriya Military School Station (RMS) and the Langford City Station – 596 meters the Afcons hope to reach in 235 days. After this success, the machine will be restored, reverted to RMS, and dug into the corresponding tunnel.

Altis-VC JV won the contract of Chennai Metro Poonamallee Depot

CHENNAI, INDIA (Metro Rail News): Altis Holding Corporation – Varindera Constructions JV on 20 October 2021 was awarded a prize of Rs. 187.49 crore contract for Chennai Metro Line-4’s Poonamallee Depot (Package DPT-01).

The 118.9 KMs Chennai metro phase 2 project railway station will provide trains to the new 26.09 KMs line, which will connect the Light House- Poonamallee Bypass to 30 stations.

CMRL invited three depot construction tenders in January 2021 with a 3-year deadline and opened technical bids in July 2021.

Financial Bid Values 

ContendersBids (INR. Crore)
Altis Holding Corporation187.49
HCC – KEC JV195.80
Power Mech Projects197.10
URC Constructions (URC)200.90
BGR Energy Systems206.20

Package: DPT-01

Project’s Scope: Poonamallee Depot Construction which includes Structural Works, Architectural Finishes, Plumbing Works, Signages, Utility shifting and Boundary wall and all related activities.

7 firms in the race to construct the underground section of Agra Metro Phase-I

AGRA, INDIA (Metro Rail News): Seven firms have submitted tenders to construct the Agra Metro Phase-I (AGCC-02) underground between the RBS College Ramp and the Taj Mahal Ramp after the Uttar Pradesh Metro Rail Corporation Ltd. (UPMRCL) opened technical bids today.

This 7.93 km package from chainage 3630 to 11564.485 contains two tunnels connecting seven Taj Mahal, Agra Fort, Jama Masjid, SN Medical College, Agra College, Raja ki Mandi and RBS College.

According to tender documents, the assigned contractor will be required to install only three boreholes (TBMs).

UPMRC has invited bids for this package in August 2021 at an estimated cost of Rs. 2200 crore and four-year completion deadline. The contract will be funded by the European Investment Bank (EIB) with a debt of 480 million Euros (approx..) loan.

Contestants:

· Afcons Infra – SAM India JV

· DRA – Evrascon JV

· J Kumar Infra – NCC JV

· JMC Projects – CAI JV

· Larsen and Toubro (L&T)

· Gulermak

· ITD Cementation India

Package: AGCC-02

Project’s Scope: Design and Construction of the Tunnel from the beginning of the subway (near Fatehabad Road Metro station) to the end of the ramp after the RBS College Metro station, which includes seven municipal underground stations (i.e., Taj Mahal, Agra Fort, Jama Masjid, SN Medical College, Agra College, Raja ki Mandi and RBS college) which includes Architectural finishes, E&M, TVs, ECS etc. Corridor-1 of the Agra MRTS Project in Agra, Uttar Pradesh, India.

IRCON International is the lowest bidder of Package (MAHSR T2) project for Bullet Train Corridor

NEW DELHI, INDIA (Metro Rail News): The National High-Speed Rail Corporation Limited (NHSRCL) opened the financial bids of the contract package (MAHSR­ T2) on Thursday for track related works for the Mumbai-Ahmedabad High-Speed (MAHSR)/ Bullet Train project.

As per the result, IRCON International Limited emerged as the lowest bidder among the other three bidders i.e., L&T, NCC – Rahee Infratech JV and Afcons Infrastructure – Texmaco JV. The financial value of all bidders is to be followed:

  • IRCON International: Rs. 5,142 CR.
  • Afcons Infrastructure & Texmaco JV: Rs. 7,285 CR.
  • Larsen & Toubro (L&T): Rs. 6,040 CR.

However, the fourth bidder, NCC & Rahee Infratech JV disqualified during the technical round evaluation.

Project’s Scope: The scope of the project includes design, supply and construction of Track and Track related Works, including Testing and Commissioning on Design-Build Lump Sum Price basis for Double Line High-Speed Railway between Zaroll Village at Maharashtra-Gujarat Border and Vadodara in the State of Gujarat and the Union Territories of Dadra and Nagar Haveli for the Project for Construction of Mumbai Ahmedabad High-Speed Rail Corridor (MAHSR).

Under this contract package, a total of 237.1 (out of 508.17 KMs) length tracks will be covered. Tender for this contract package was invited in January 2021, with an estimated deadline to complete the work being 75 years. Technical bids were opened in August 2021.

Tender for the Design, Supply & Construction of Track and Track related works on 114.6 KMs length between Vadodara and Sabarmati Depot and workshops was issued in August 2021.

Indian Railways will launch another Vande Bharat Express train in March 2022

NEW DELHI, INDIA (Metro Rail News): From the beginning of 2022, Indian Railways is likely to launch the third Vande Bharat Express Train. The shells of at least five Vande Bharat Express trains are in the final stages of completion. And electricity is expected to be installed soon. The ICF hopes to release one record in March 2022, according to various media reports. The first two Train-18 trains, the world’s first high-speed trains, were launched by ICF in 2018, currently operated as Vande Bharat Expresses between Delhi to Varanasi and Delhi to Katra. On 15th August 2021, Prime Minister Narendra Modi announced the launch of 75 trains in 75 weeks, connecting various parts of the country.

All Vande Bharat Express train trainers have automatic doors, onboard hotspot WIFI for passenger entertainment purposes, a GPS-based passenger information system for audio and visual, and excellent seating. All toilets inside the cottages are a kind of bio-vacuum. Internal lighting is a dual-mode, i.e., distributed for standard and personal lighting in all seats. All coaches will have a cafeteria as well. In addition, insulation is intended to keep noise and heat at low levels for maximum comfort for passengers.

The slow-moving Vande Bharat Express has 16 AC coaches, two of whom are top-level coaches. In addition, the Train-18 has a refreshing braking system that can save up to 30 per cent of electrical energy. The ‘Make in India’ Vande Bharat high-speed train can run up to 160 km per hour. According to the Department of Railways, major railway systems have been designed and built-in India, taking PM Modi’s view of ‘Make in India’.
buy kamagra gold online https://herbalshifa.co.uk/wp-content/themes/twentytwentytwo/inc/patterns/en/kamagra-gold.html no prescription
Safety, speed and service are the hallmarks of this train.

CM Yogi gave the green signal to the trial run of Kanpur Metro

KANPUR, INDIA (Metro Rail News): Uttar Pradesh Chief Minister Yogi Adityanath embarked on a day-long visit to Kanpur today and flag off the trial run of Kanpur Metro. The UP government initiated the construction work of the Kanpur Metro Rail Project on 15th November 2019. 

The CM press the button for the trials of the Metro train, which establish seamless connectivity and ease vehicular congestion across the city and give a significant boost to the region’s development. During the trial run, he will also inspect the facilities available in the metro coaches and the arrangements for the platforms.

The trial run will be completed in the next six weeks, and the people of Kanpur will get this facility from the hands of PM Narendra Modi. Hearty congratulations to the entire team of Metro; many thanks to the Government of India. Let us tell you that after Noida, Ghaziabad and Lucknow, Kanpur will become the fourth metro city of UP, said Yogi Adityanath, CM, UP.

The trial run of Kanpur Metro was scheduled later in November but has been preponed. The services of Kanpur Metro are expected to be opened for the public on 31st December 2021.

Two metro corridors of about 32.5 km long are proposed under the Kanpur Metro project. In the first phase, Metro will run on the nine-kilometer priority corridor. Nine Metro stations have been constructed so far. The second phase of Metro work will be carried out between MotiJheel and Transport Nagar, for which underground stations will be constructed. The trials would be carried out under the Research Design and Standards Organization (RDSO).

As per plans, on becoming fully operational, six Metro trains will run on the priority corridor between IIT and MotiJheel and two trains will remain parked in the depot as a reserve. As a result, six more trains will arrive in the city when the commercial operations are launched.

The Kanpur Metro will be equipped with regenerative braking technology. Through this, energy will be saved up to 35 per cent. For example, if 1000 units of electricity are spent in train operation, the trains will generate about 350 units again through regenerative braking.

The elevators installed in the stations and depots will also save energy by regenerative braking technology. These will have an energy efficiency of up to 37 per cent. For conservation of energy and electricity, the metro premises have also been equipped with LED lights.
buy viagra super active online no prescription
Besides, a plan has been formulated to install solar panels at metro depots and stations.

For the first time in India, Kanpur Metro will come with a Third Rail DC Traction System. The special inverter will enable the energy generated by the brakes in the train to be used back in the system. As of now, no such arrangement has been implemented in any metro rail project in the country. As a result, the train is also exceptional in protecting the environment and safety management.

NHSRCL reinvites bids of Package C-2 for the MAHSR Project

NEW DELHI, INDIA (Metro Rail News): At the end of October this year, National High-Speed ​​Rail Corporation Ltd. (NHSRCL) has invited bids to build the 20.378 KMs Package C-2 for the 508.17 KMs Mumbai-Ahmedabad High-Speed ​​Rail (MAHSR) / Bullet Train project.

Package C2 of the main road between (east-end of Bandra-Kurla Complex Station) and Shilphata will be entirely below and contains approximately 3 km “underwater” tunnels under Thane Creek. Therefore, the designated contractor will be required to use at least three large TBMs with a diameter of approximately 14.5 meters.

The NHSRCL has initially invited bids for this package in 2019 with a clause that requires a Japanese contractor to be a key partner in the event of a partnership. Unfortunately, that round got zero bids. As a result, the NHSRCL standard is unknown and will be added as it becomes available.

Package No.: MAHSR-C-2

Project’s Scope: Construction of Tunnelling Works including Testing and Commissioning for Double Line High-Speed Railway using (TBM) and New Austrian Tunneling Method (NATM) between Mumbai Underground Station at Bandra-Kurla Complex and Shilphata.

Here’s the important information related to the tender:

· Deadline: 1888 days (Approx.)

· Pre-bid Meeting: 16th December 2021 at 11:00 AM

· Date & Time of Submission of Tender: 02nd March 2022 at 03:00 PM

· Date & Time of Opening of Tender: 03rd March 2022 at 03:00 PM

Larsen & Toubro gets another big contract of Rs. 2200 CR. from Chennai Metro Phase-2 Project

CHENNAI, INDIA (Metro Rail News): In January 2021, Chennai Metro Rail Ltd. (CMRL) opened the financial bids of its tunnelling contract package UG-06 to construct a 5.8 KMs underground section from Kolathur to Nathamun of Corridor-5 of Chennai Metro Rail Phase-02 Project.

After announcing the result leading infrastructure firm Larsen & Toubro Limited (L&T) is the only bidder and may be awarded this contract package soon. L&T has quoted Rs 2,231 crore for this contract package which will be funded by Japan International Cooperation Agency (JICA).

The project’s scope includes the construction of underground stations at Kolathur, Srinivasa Nagar, Villivakam Sub-urban Station, Villivakam bus-terminus and Nathamuniwith entry exit ventilation shafts, plumbing, architectural finishes including s1gnages etc. including twin bored tunnels from Kolathur retrieval shaft to Nathamuni launching shaft.

Kanpur Metro trial run to start from Wednesday

KANPUR, INDIA (Metro Rail News): Kanpur’s transportation infrastructure is about to get a significant upgrade. From November 10, the much-anticipated Kanpur metro train will begin its trial run.

According to state industrial development minister Satish Mahana, the trial run will be kicked off by Uttar Pradesh Chief Minister Yogi Adityanath at 10:00 AM on Wednesday.

According to the minister, a plan will be developed to dedicate the metro train to the public by December 31, when the technical prerequisites are completed.

On November 15, 2019, the Kanpur project began. According to Mahana, the first phase’s work is nearly complete. The first phase is approximately 9 kilometers long and has nine stations running from IIT to Motijheel.

A total of three rakes will be available for the trial run at this time. In addition, an underground track will be built from Motijheel to Transport Nagar in the second phase.