L&T and J Kumar Bags Delhi Metro Phase IV Silver Line’s Underground Work

Date:

Share post:

Delhi (Metro Rail News): Larsen & Toubro and J Kumar Infraprojects submitted the lowest bids on Thursday for the construction of two underground tunnelling packages (DC-09 and DC-08) for the 65.1 km Silver Line of the Delhi Metro Phase 4 project.

Both civil contracts were originally awarded to Afcons Infrastructure and Tata Projects Ltd. (TPL) in November-December 2021. All eligible bidders were asked to submit revised financial proposals because their bids were much higher than the Delhi Metro Rail Corporation’s (DMRC) predictions.

Both packages have a 42-month deadline and are backed by an Rs 8,390 crore ODA loan from JICA. DMRC initially had an estimate of 1349 Crores and Tata Projects Ltd. (TPL) were the original winner.

Package DC-08: This 6.116-kilometre section of the 23.622-kilometre Silver Line runs from Aerocity to Kishangarh and has four stations: Aerocity, Mahipalpur, Vasant Kunj, and Kishangarh.

CompanyBid Value (Crore)
J Kumar Infraprojects1611.85
Tata Projects1639.02
L&T1684.35
Afcons1854.99
ITD Cem1926.29
Gulermak2237.64

The work includes: Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box and four Underground stations namely Aerocity, Mahipalpur, Vasant Kunj and Kishangarh with Entry/Exits & Connecting subways from chainage (-) 760 mt. to 5356.285 mt. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.

Package DC-09: This 6.51-kilometre section, with twin-tunnels smack-dab in the middle of the Silver Line, will run from Kishangarh Station’s east end (chainage 5356.285) to a ramp (chainage 11867.000) west of Saket G Block Station, passing through four stations: Chhattarpur (interchange with Yellow Line), Chhattarpur Mandir, IGNOU, and Neb Sarai.

DMRC initially had an estimate of 1428 Crores and Afcons infrastructure was the original winner.

CompanyBid Value (Crore)
L&T1737.22
Afcons1739.64
Gulermak1940.90
ITD Cem2028.40

The work includes: Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box, Underground Ramp and four Underground stations namely Chhattarpur, Chhattarpur Mandir, IGNOU and Neb Sarai with Entry/Exits & Connecting subways from chainage 5356.285 mtr. to 11867.000 mtr. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.

J Kumar and L&T’s bids were 19% and 22% more than DMRC’s predictions, the chances of contracts being awarded are expected to be slim. Both firms’ management will most likely be invited to negotiations by DMRC, and if those fail, both will be going into a re-tender.

Following this development, here is the status of all four JICA-funded Phase 4 underground packages.

DELHI Metro Ppase IV Civil PackageStatus
Package DC-05: Derawal Nagar to RK Ashram, 7.46 km underground section with 6 stationsAwarded to Afcons Infra
Package DC-08: Aerocity to Kishangarh, 6.11 km underground section with 4 stationsJ Kumar is the lowest bidder
Package DC-09: Kishangarh to Saket G-Block, 6.88 km underground section with 4 stationsL&T is the lowest bidder
Package DC-07: Sangam Vihar to Tughlakabad, 6.477 km underground section with 3 stationsAwarded to Afcons Infra
Kishore Kumar
Kishore Kumarhttp://www.symbrojmedia.com
Kishore Kumar has completed Post-Graduate Diploma from IIMC and is currently working with Metro Rail News.

1 COMMENT

  1. Sir I’m dileep Kumar Raikwar electrical electrician in the DC 08 vasant kunj side Jkumar I need job please

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

NCRTC Initiates Train Trial Runs between Sahibabad & New Ashok Nagar RRTS Station

Delhi (Metro Rail News): The long-awaited Delhi Section of the Delhi Meerut RRTS corridor has finally advanced as...

Noida Metro Witnessed a Steady Growth in Ridership in September

Noida ( Metro Rail News): After reaching a remarkable milestone last month, Noida Metro's ridership trend is still...

Maha Metro Floats Tender for Pune Metro’s Swargate – Katraj Extension

Pune (Metro Rail News): Maharashtra Metro Rail Corporation (Maha Metro) floated tenders on 4 October for the civil...

Delhi Metro’s TBM-2 Records Breakthrough at Chhatarpur Mandir Station of Line 10

Delhi (Metro Rail News): Larsen and Toubro’s Tunnel Boring Machine DZ1123 (TBM-2) achieved a breakthrough on 5 October...