Johnson Lifts Wins Elevator Contract of Kochi Metro Phase 2

KOCHI (Metro Rail News): The Kochi Metro Rail Limited (KMRL) has announced Johnson Lifts Private Limited as the lowest bidder for the elevator contract of Kochi Metro Phase 2 Project. 

KMRL invited bids for this contract with a 730 days deadline.Technical bids were opened on 29 September 2025 announcing that 2 firms have submitted bids for the contract and the technical evaluation of the submitted bids occurred on 27 Nov 2025. On the same day, financial bids were opened revealing that Johnson Lifts is the lowest bidder for the contract and the firm received LoA from Maha-Metro. 

Financial Bid Values  

FirmBid Value 
Johnson Lifts Private Limited₹ 17.4 Cr
Otis Elevator Company (India) Limited₹ 19.7 Cr

Contract Scope of Work: Design, Manufacturing, Supply, Installation, Testing and Commissioning of Heavy Duty Machine Room Less Elevators For Phase II of The Kochi Metro Rail Project.

The Phase 2 of Kochi Metro consists of one metro corridor (Pink Line) which spans 11.2 km from JLN Stadium to Infopark covering 11 stations.

Recently, KMRL also announced Schindler India Private Limited as lowest bidder for the escalator contract of the Kochi Metro Phase 2.


Join the 6th edition of InnoMetro to explore how the progressions in AI are improving the railway systems, including ticketing, rolling stock, and signalling. Witness the innovation from 200+ exhibitors at India’s leading show for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

Chennai Metro Phase 2: Fujitec India Receives LoA for Escalator Contract of Line 5 

CHENNAI (Metro Rail News): Fujitec India has received a Letter of Acceptance (LoA) from Chennai Metro Rail Corporation (CMRL)  for the escalator contract of Chennai Metro Phase 2’s Corridor 5. 

CMRL invited bids for the contract with a 1940 days deadline. Technical bids were opened on 6 Nov 2024 revealing that only one firm had submitted for the contract. The technical evaluation of the bid took place on 22 May 2025.

The financial bids for the contract were opened on 23 May 2025 and the financial evaluation of the bid occurred on 27 November 2025. After the financial evaluation round Fujitec India was declared as the lowest bidder and received  LoA for the contract. 

Screenshot 2025 11 29 103851

Fujitec India Bid Value: ₹ 147.3 Cr 

Contract Scope of Work:  Design, Manufacture, Supply, Installation, Testing and Commissioning of Heavy-Duty Escalators for CMRL Phase II – Corridor 5 (From Madhavaram Depot Metro to Koyambedu Metro stations) 

The Phase 2 of Chennai Metro spans  118.9 km and consists of three new metro corridors.

Line Route Elevated Length Underground Length Total Length 
Line 3 ( Purple Line) Madhavaram – SIPCOT 219.1 km 26.7 km 45.8 km 
Line 4 (Orange Line) Light House – Poonamallee Bus Depot16 km 10.1 km 26.1 km 
Line 5 (Red Line) Madhavaram – Sholinganallur41.2 km 5.8 km 47 km 

Join the 6th edition of InnoMetro to explore how the progressions in AI are improving the railway systems, including ticketing, rolling stock, and signalling. Witness the innovation from 200+ exhibitors at India’s leading show for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

Rahee Infratech Receives LoA for Track Contract of Nagpur Metro Phase 2 

NAGPUR (Metro Rail News): Rahee Infratech Limited has received a Letter of Acceptance (LoA) for the track contract of Nagpur Metro Phase 2.

Maha-Metro invited bids for this contract with a 913 days deadline. Technical bids were opened on 1 Nov 2024 announcing that 2 firms have submitted bids for the contract. Technical evaluation of the submitted bids occurred on 20 Jan 2025. 

Financial bids for the contract were opened on 27 Jan 2025 and financial evaluation of the bids occurred on 20 March 2025. During the financial evaluation round Rahee Infratech was declared as the lowest bidder for the contract and on 25 Nov, the firm received LoA for the contract. 

Screenshot 2025 11 28 140831

Financial Bid Values 

FirmBid Value 
Rahee Infratech Limited₹ 174.1 Cr
Texmaco Rail and Engineering Limited₹ 217.4 Cr

Contract Scope of Work: Design, Supply, Installation, Testing and Commissioning of Ballasted/ Ballast-less track in At Grade section of Reach 1A and elevated viaduct of Reach 2A & Reach 4A of NMRP Phase-2 including supply of 1080Grade HH Rails, track fastenings, 1 in 9 R300 Ballasted/Ballastless turnouts & Derailing switches and other miscellaneous works. 

The under-construction Phase 2 of Nagpur Metro spans 43.8 km. The Nagpur Metro Phase 2 extends the two existing lines of Phase 1 to Kanhan in the north, Butibori MIDC in the south, Transport Nagar (Kapsi) in the east and Hingna in the west. 

Nagpur Metro Phase-II consists of the following 4 extensions of 2 corridors of Phase I. 

Line Route Length 
Orange Line Khapri – MIDC ESR 18.5 Km
Orange Line Automotive Square – Kanhan River13 km
Aqua LinePrajapati Nagar – Transport Nagar5.6 km
Aqua Line Lokmanya Nagar – Hingna6.7 km

Explore how AI-integrated systems are improving comfort, connectivity, and accessibility for passengers across metro and rail networks at the 6th edition of InnoMetro, India’s leading expo for the Metro & Railway industry which is going to be held on  21-22 May 2026 at Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

Fujitec India Receives LoA for Escalator Contract of Chennai Metro Phase 2

CHENNAI (Metro Rail News): Fujitec India has received a Letter of Acceptance (LoA) from Chennai Metro Rail Corporation (CMRL)  for the escalator contract of Chennai Metro Phase 2’s Corridor 3. 

CMRL invited bids for this contract with a 2070 days deadline. Technical bids were opened on 6 Nov 2024 announcing that only one firm had submitted bids for the contract. Technical evaluation of the bid occurred on 5 June 2025. On 6 June 2025 financial bids were opened for the bid and financial evaluation of the bids took place on 27 November. During the financial evaluation round Fujitec India was declared as the lowest bidder for the contract and received LoA for the contract from CMRL. 

Screenshot 2025 11 28 133746

Fujitec India Bid Value: ₹ 453.6 Cr

Contract Scope of Work: Design Manufacture Supply Installation Testing and Commissioning of Heavy Duty Escalators and Travelators for CMRL Phase II Corridor 3 (From Madhavaram Milk Colony Metro to Sholinganallur Metro stations). 

The Phase 2 of Chennai Metro spans  118.9 km and consists of three new metro corridors.

Line Route Elevated Length Underground Length Total Length 
Line 3 ( Purple Line) Madhavaram – SIPCOT 219.1 km 26.7 km 45.8 km 
Line 4 (Orange Line) Light House – Poonamallee Bus Depot16 km 10.1 km 26.1 km 
Line 5 (Red Line) Madhavaram – Sholinganallur41.2 km 5.8 km 47 km 

Explore how AI-integrated systems are improving comfort, connectivity, and accessibility for passengers across metro and rail networks at the 6th edition of InnoMetro, India’s leading expo for the Metro & Railway industry which is going to be held on  21-22 May 2026 at Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

Schindler India Becomes L1 for Escalator Contract of Kochi Metro Phase 2

KOCHI (Metro Rail News): The Kochi Metro Rail Limited (KMRL) has announced Schindler India Private Limited as lowest bidder for the escalator contract of the Kochi Metro Phase 2.

KMRL invited bids for this contract with a 730 days deadline. Technical bids were opened on 29 September announcing that 3 firms submitted bids for this contract. The technical evaluation of the submitted bids took place on 27 Nov 2025 and all the 3 firms qualified that round. Furthermore, financial bids for the qualified bids were opened on the same day and after a financial evaluation round Schindler India was declared as the lowest bidder for the contract.

Financial Values 

Firm Bid Value 
Schindler India Private Limited₹ 36.5 Cr
Johnson Lifts Private Limited₹ 43.5 Cr
Otis Elevator Company (India) Limited₹ 49.3 Cr

Contract Scope of Work: Design, Manufacturing, Supply, Installation, Testing and Commissioning Of Heavy Duty Escalators For Phase II of The Kochi Metro Rail Project.

The under construction Phase 2 of Kochi Metro consists of one metro corridor (Pink Line) which spans 11.2 km from JLN Stadium to Infopark covering 11 stations.

Station Names: Jawaharlal Nehru Stadium (new station box), Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal (formerly Kunnumpuram), Kakkanad Junction, Cochin SEZ (Special Economic Zone), Chittethukara, KINFRA (formerly Rajagiri), InfoPark 1 / Smart City 1, and InfoPark 2 / Smart City 2


Explore how AI-integrated systems are improving comfort, connectivity, and accessibility for passengers across metro and rail networks at the 6th edition of InnoMetro, India’s leading expo for the Metro & Railway industry which is going to be held on  21-22 May 2026 at Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

South Central Railway Submits Final Alignment for Hyderabad-Chennai High-Speed Rail Project

CHENNAI (Metro Rail News): The 778-km Hyderabad-Chennai high-speed rail project has gained momentum as the South Central Railway submitted the final alignment, which will be incorporated in the detailed project report, to the government of Tamil Nadu. Following the approval of the state government, the DRP for this high-speed rail corridor will be finalised. 

The alignment of this corridor has been revised, which was suggested by the government of Tamil Nadu. The revision was made to include a station at Tirupati. 

This high-speed rail corridor will reduce the travel time from a 12-hour journey to around 2 hours and 20 minutes. To facilitate transit-oriented development and create commercial hubs, the Indian Railway has requested 50 acres of land around each station. 

The South Central Railway has urged the state transport department to finalise the alignment and provide approval for land acquisition at the earliest. In addition to this, SCR has suggested that the state transport department shall include this high-speed rail corridor in Tamil Nadu’s long-term infrastructure master plan.

The project features a complex underground tunnel in Tamil Nadu. It will span about 11.6km and require meticulous planning and thorough geotechnical investigation to identify the construction methods. The alignment of this corridor has been decided as per the surveys conducted by RITES. This corridor reflects India’s efforts to establish high-speed rail networks beyond MAHSR.


Discover how AI is bringing the next phase of sustainable urban rail mobility for Viksit Bharat at InnoMetro 2026, India’s prime exhibition and conference for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi.

Register Now: https://innometro.com/visitor-registration/

Adani Enterprises Receives LoA for Sonprayag-Kedarnath Ropeway Project

AHMEDABAD (Metro Rail News): Adani Enterprises Ltd. has received a LoA from National Highways Logistics Management Ltd. (NHLML) for the construction of the ropeway system between Sonprayag and Kedarnath. The project will be carried out by the Roads, Metro, Rail, and Water (RMRW) division of AEL.

Adani Enterprises Ltd. (AEL) plans to invest ₹4,081 crore in developing the ropeway between Sonprayag and Kedarnath. The proposed alignment spans 12.9 km and is intended to replace the existing long and difficult trek, which will reduce travel time to about 36 minutes. The system is being designed to handle a passenger flow of 1,800 persons per hour in each direction.

The ropeway is being developed under the National Ropeways Development Programme (Parvatmala Pariyojana). It is structured as a Public-Private Partnership (PPP) project, with an estimated construction period of six years. After completion, Adani Enterprises Ltd. will operate the system for a concession period of 29 years. In addition to improving accessibility to Kedarnath, the project is expected to support local employment and contribute to tourism-related economic activity in the area.

On this occasion, Mr Gautam Adani, Chairman of the Adani Group, said that “The Kedarnath ropeway is more than an engineering project – it is a bridge between devotion and modern infrastructure.” He further mentioned that “By making this sacred journey safer, faster and more accessible, we honour the faith of millions while creating new opportunities for Uttarakhand’s people through our partnership with NHLML and the Government of Uttarakhand. This prestigious project reflects our commitment to building infrastructure that not only serves the nation but also uplifts its people.”


Discover how AI is bringing the next phase of sustainable urban rail mobility for Viksit Bharat at InnoMetro 2026, India’s prime exhibition and conference for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi.

Register Now: https://innometro.com/visitor-registration/

Becquerel Industries Secures 2 Geotechnical Contracts for Bangalore Metro Phase 3A

BANGALORE (Metro Rail News): Bangalore Metro Rail Corporation has declared Becquerel Industries Private Limited as the lowest bidder for two contracts involving geotechnical investigation works for the elevated sections of Bangalore Metro Phase 3A.  

Contract 1

Tender Information

Tender Id2025_BMRCL_251149_1
Tender NoBMRCL/Phase-3A/GTI/P1/2025/138
Cost of work₹1.60 crore
Contract Period150 Days

Brief scope of work: Carrying out Geo-Technical Investigation services for the construction of Elevated Metro Corridor from Sarjapura Station to Carmelaram Station (Chainage 0.496 km to 10.356 km), including the Depot, under Phase-3A of the Bangalore Metro Rail Project.

Bidders’ Details: 

Bidder NameBid Value / Award AmountRankStatus
Becquerel Industries Private Limited₹ 1.6 CrL1potential-aoc
RITES Limited₹ 1.6 CrL2accepted-financial
Civilmantra Infracon Limited₹ 1.7 CrL3accepted-financial
Space Engineers Consortium Private Limited₹ 1.7 CrL4accepted-financial
IDAX Consulting and Research Pvt. Ltd.₹ 1.7 CrL5accepted-financial
CEG Test House and Research Centre Pvt. Ltd.₹ 2 CrL6accepted-financial
Bureau Veritas (India) Pvt. Ltd.₹ 2.2 CrL7accepted-financial
Techpro Engineers Pvt. Ltd.₹ 2.8 CrL8accepted-financial
Secon Private Limited₹ 2.8 CrL9accepted-financial
Synergy Testing House LLP₹ 2.9 CrL10accepted-financial
Infinite Civil Solutions Pvt. Ltd.₹ 5.1 CrL11accepted-financial

Contract 2

Tender Information

Tender Id2025_BMRCL_251156_1
Tender NoBMRCL/Phase-3A/GTI/P2/2025/139
Cost of work₹1.26 crore
Contract Period150 Days

Brief scope of work: Carrying out Geo-Technical Investigation services for the construction of Elevated Metro Corridor from Carmelaram Station to Null Point near Koramangala 3rd Block Station (Chainage 10.356 km to 19.578 km) under Ph-3A of the Bangalore Metro Rail Project.

Bidders’ Details: 

Bidder NameBid Value / Award AmountRankStatus
Becquerel Industries Private Limited₹ 1.2 CrL1potential-aoc
Civilmantra Infracon Limited₹ 1.3 CrL2accepted-financial
Mercury Engineering Consultancy₹ 1.3 CrL3accepted-financial
RITES Limited₹ 1.3 CrL4accepted-financial
IDAX Consulting and Research Pvt. Ltd.₹ 1.4 CrL5accepted-financial
CEG Test House and Research Centre Pvt. Ltd.₹ 1.7 CrL6accepted-financial
Bureau Veritas (India) Pvt. Ltd.₹ 1.8 CrL7accepted-financial
Secon Private Limited₹ 2.2 CrL8accepted-financial
Synergy Testing House LLP₹ 2.3 CrL9accepted-financial
Infinite Civil Solutions Pvt. Ltd.₹ 4 CrL10accepted-financial

Bangalore Metro Phase 3A

Bangalore Metro Phase 3A is planned to improve connectivity between the rapidly growing Sarjapur area in the southeast and Hebbal in the north. The corridor spans about 36.6 km and includes both elevated and underground sections, with a total of 28 stations. The elevated section spans about 22.14 km & underground 14.45 km. The project has an estimated cost of around ₹28,400 crore. Phase 3A is targeted for completion by 2036. 


Discover how AI is bringing the next phase of sustainable urban rail mobility for Viksit Bharat at InnoMetro 2026, India’s prime exhibition and conference for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi.

Register Now: https://innometro.com/visitor-registration/

Maha-Metro Floats Tender to Appoint GC for Phase 1 & 2 of Pune Metro 

PUNE (Metro Rail News): Maha-Metro (Maharashtra Metro Rail Corporation Limited) has invited bids for the appointment of a General Consultant for the extension of Phase 1 and Phase 2 of the Pune Metro Rail Project. 

Tender Details 

Closing Date23 Dec 2025
Pre Bid Meeting 4-12-2025 
EMD Rs. 1.83 Cr 
Tender IdP2-Consul-01(R)/2025 (NCB) 
Tender NoP2-Consul-01(R)/2025 (NCB) 

Contract Duration: 60 Months from the date of issue of LoA.

Contract Scope of Work: Engagement Of General Consultant For Pune Metro Rail Project For Extension Of Phase -i And Phase -ii Projects.

The Pune Metro Phase 1 project spans 31.254 km and consists of two operational metro corridors. 

Corridor Route Length Total no. of Stations 
Line-1 (Purple Line) Pimpri Chinchwad Municipal Corporation (PCMC) – Swargate16.589 km14 Stations
Line-2 (Aqua Line)Vanaz – Ramwadi
14.665 km16 Stations

Maha Metro initially proposed an 82.5 km network under Phase 2 of the Pune Metro project, which includes extensions of the existing Aqua Line in both directions and the addition of two new metro corridors. So far, routes totalling 44.09 km have received approval for construction.


Discover how AI is bringing the next phase of sustainable urban rail mobility for Viksit Bharat at InnoMetro 2026, India’s prime exhibition and conference for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi.

Register Now: https://innometro.com/visitor-registration/

RVNL Wins OHE Upgradation Work Contract from North Eastern Railway

North Eastern Railway has declared Rail Vikas Nigam Limited (RVNL) as the lowest bidder for upgrading the existing overhead equipment (OHE) system in Lucknow division.

Contract Value: Rs. 180 Crores 

Contract Duration: 24 Months

Contract Scope of Work: design, supply, erection, testing & commissioning of OHE modification and feeder wire work of 2×25 kV traction system for capacity upgradation of UTR-MWP section (184 RKM/368 TKM) in Lucknow division of Northern Railway,” 

Recently, RVNL also received  a Letter of Acceptance (LoA) from the Secunderabad Division of South Central Railway for the modernization and upgrading of the existing Overhead Equipment (OHE) system.

The contract included the design, supply, erection, testing, and commissioning for the upgradation of the existing 1x25kV system to a 2x25kV AT feeding system, including feeder and earthing works, in the Ramgundarn (RDM) Kazipet (KZJ) section of Secunderabad division under South Central Railway.


Discover how AI is bringing the next phase of sustainable urban rail mobility for Viksit Bharat at InnoMetro 2026, India’s prime exhibition and conference for metro & railways which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi.

Register Now: https://innometro.com/visitor-registration/

Tamil Nadu CM Urges PM to Reconsider Rejected Coimbatore & Madurai Metro Projects

Tamil Nadu Chief Minister Mr. M. K. Stalin wrote a detailed letter to Prime Minister Narendra Modi, expressing deep disappointment over the rejection of proposals for Metro Rail projects in Coimbatore and Madurai on 22 Nov 2025.. He urged the Prime Minister to direct the Ministry of Housing and Urban Affairs (MoHUA) to reconsider the decision.

On November 14, the Union Ministry of Housing and Urban Affairs, in a communication to the Tamil Nadu government, returned the Detailed Project Reports (DPRs) for both projects. The ministry cited that, according to the 2011 Census, Coimbatore’s population is 15.84 lakh, while Madurai’s is below 15 lakh. Both cities therefore fall short of the two million population threshold required under Clause D(ii)(a) of the 2017 Metro Rail Policy to initiate metro planning. The ministry further noted that metro projects are highly capital-intensive and must be undertaken with careful consideration to ensure long-term financial sustainability.

Mr. Stalin said in his letter “Tamil Nadu, being the most urbanised State in the country with a high per capita private vehicle ownership, needs high-capacity public transport alternatives in all its large growth engine cities. Towards this, we had prepared the DPRs for Coimbatore and Madurai Metro Rails and forwarded the same to MoHUA for approval,”as reported by The Hindu. 

Mr. Stalin mentioned “Considering the high priority accorded to these two projects, we were continuously following up with the relevant Ministry. In this backdrop, the rejection of this request has taken us by complete surprise. It has created deep resentment amongst the people of the two cities that their deserving needs have been rejected, as compared to similar projects sanctioned in other States,”. 

 The Chief Minister also mentioned “I wish to highlight that the population of Coimbatore LPA area had exceeded 2 million way back in 2011 itself and in the case of Madurai too, the expected population is likely to exceed it now. It is pertinent to point out at this juncture that if this 2 million criteria had been applied uniformly, many Metros in Tier-II cities like Agra, Indore, and Patna may not have materialised,”. 

The Comprehensive Mobility Plan (CMP) for Coimbatore, prepared by RITES after extensive traffic studies, had clearly identified the necessity of a Mass Rapid Transit System (MRTS) along the proposed corridors. Similarly, the CMP for Madurai, prepared in 2011, had recommended a Bus Rapid Transit (BRT) system; however, since a huge portion of the alignment would require elevated structures, it also noted that a rail-based system could be a suitable alternative. Furthermore, the subsequent Detailed Project Report (DPR) studies conducted independent traffic projections, which reinforced the justification for developing Metro Rail corridors, the Chief Minister highlighted.


Witness the innovations & AI- powered solutions in railway & metro systems from over 200 exhibitors at the 6th edition of InnoMetro. Join India’s dedicated show for the rail transit sector which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi. 

Register now: https://innometro.com/visitor-registration/

 HG Infra-Kalpataru JV Wins Civil Contract of Thane Metro 

THANE (Metro Rail News): Maha-Metro (Maharashtra Metro Rail Corporation Limited) has announced HG Infra-Kalpataru JV as the lowest bidder for the civil contract of Thane Integral Ring Metro Project. This is a joint venture , with KPIL holding 60% and HG Infra holding 40% share.

Maha-Metro invited bids for this contract with a completion deadline of 913 days. The technical bids were opened on 10 September 2025, revealing that 6 firms have submitted bids for the contract. Technical evaluation of the submitted bids was conducted on 20 November 2025, during which one firm’s bid was disqualified. Subsequently, the financial bids were opened on 21 November 2025, where Kalpataru Projects International emerged as the lowest bidder for the contract.

Financial Bid Values 

Firm Bid Value 
HG Infra-Kalpataru JV ₹ 1415 Cr
Afcons Infrastructure Limited₹ 1675.8 Cr
G.R Infraprojects Limited  ₹ 1657.8 Cr 
Larsen and Toubro Limited₹ 1836 Cr
M/S J. Kumar Infraprojects Ltd₹ 1755.9 Cr

Contract’ Scope of Work: Design and Construction of Elevated Metro Viaduct of length 20.527km between End of UG Ramp to Balkum Naka including Depot Approach Viaduct and three Special Spans for Thane Integral Ring Metro Project. 

The Thane Metro Phase 1 project, officially known as the Thane Integral Ring Metro, is a 29-kilometer mass rapid transit system featuring a single circular line with 22 stations. The corridor will trace a 29-kilometer route along the western periphery of Thane city.


Witness the innovations & AI- powered solutions in railway & metro systems from over 200 exhibitors at the 6th edition of InnoMetro. Join India’s dedicated show for the rail transit sector which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi. 

Register now: https://innometro.com/visitor-registration/

NCRTC Invites Bids for DDC Contract of Upcoming Namo Bharat Corridors

National Capital Region Transport Corporation (NCRTC) has floated a tender for the appointment of Detail Design Consultant (DDC) for the upcoming Namo Bharat Corridors. 

Tender Details 

Opening Date21 Nov 2025
Closing Date22 Dec 2025
Tender Id2025_NCRTC_255780_1
Tender NoDA/DD/COR-OF/037
EMD₹ 10,00,000

Contract Duration: 210 days

Contract Scope of Work: Engagement of Detail Design Consultant for finalization of technical parameters for future Namo Bharat Corridors.

The Public Investment Board (PIB) has recently approved two new Namo Bharat (RRTS) corridors that will connect Delhi with Gurgaon, Rewari, Sonipat, Panipat, and Karnal. Together, these projects represent an estimated investment of around Rs 65,000 crore and will now be submitted to the Union Cabinet for final approval. 

The approved RRTS Corridors has been mentioned below: 

Project Length Project Estimated Cost 
Sarai Kale Khan-Bawal RRTS corridor 93-kmRs 32,000 crore
Sarai Kale Khan- Karnal RRTS corridor 136 km Rs 33,000 crore

The Delhi–Meerut RRTS corridor is currently the only operational Regional Rapid Transit System in India. The corridor spans 82 km connecting Delhi, Ghaziabad, and Meerut. At present, a 55-km section between New Ashok Nagar and Meerut South, comprising 11 stations, is operational. 


Witness the innovations & AI- powered solutions in railway & metro systems from over 200 exhibitors at the 6th edition of InnoMetro. Join India’s dedicated show for the rail transit sector which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi. 

Register now:https://innometro.com/visitor-registration/

Bids Invited for Rolling Stock Contract of Chennai Metro Phase 1 

CHENNAI (Metro Rail News): Chennai Metro Rail Limited (CMRL) has invited bids for the rolling stock contract of Chennai Metro Phase 1 which spans 45.046 km and comprises two operational metro corridors.

Screenshot 2025 11 22 114951

Tender Details 

Opening Date21 Nov 2025
Closing Date19 Feb 2026
Tender Id2025_CMRL_886623_1
Tender NoCMRL / PHASE 1 / SYS / ARE05 / 2025
EMD₹ 24,00,00,000

Contract Duration: 1410 days + 730 (DNP) days 

Contract Scope of Work: Design, Manufacture, testing, commissioning of Standard gauge metro rolling stock ( Electrical multiple units) and depot Machinery & plant and training of personnel.  

 Chennai Metro Phase 1 spans 45.046 km and comprises two operational metro corridors.

Chennai Metro Phase 1 
Line Route Length Total No. of Stations 
Line 1 (Blue Line) Chennai Airport – Washermanpet23.10 km17 Stations 
Line 2 (Green Line) Chennai Central – St. Thomas Mount 22 km17 Stations 