51 Trainsets’ Deal Closed for Bengaluru Suburban Rail: K-RIDE & ICF Signed ₹1,565 cr Contract

0
16
51 Trainsets’ Deal Closed for Bengaluru Suburban Rail: K-RIDE & ICF Signed ₹1,565 cr Contract

Bengaluru (Metro Rail News): The long-pending issue concerning train procurement for the Bengaluru Suburban Rail Project (BSRP) has moved forward with the signing of a Memorandum of Understanding (MoU) between Integral Coach Factory (ICF) and K-RIDE for the manufacture and supply of 51 rakes, each comprising three-car trainsets, for the project.

The MoU was signed on 1 September at Integral Coach Factory, Chennai, in the presence of Shri Lakshman Singh, Managing Director, K-RIDE/Bi-RIDE, and Shri Manish Agarwal, General Manager, ICF, Chennai. The signing ceremony was also attended by officials from K-RIDE and ICF.

A Closer Look at Progress of Bengaluru Suburban Rail Project

PM Modi laid the foundation of the BSRP on June 20, 2022. The ₹15,767-crore project will span 148.17 km across 4 corridors.  The project has crawled at a very slow pace and faced multiple roadblocks, including delays in land acquisition and pending transfer of land from the state government. 

100% Land Acquisition Completed for Only 1 of 4 Corridors

Nearly four years after work commenced on the Bengaluru Suburban Rail Project (BSRP), land acquisition has been completed for only one of the project’s four proposed corridors, according to details furnished by the Union Government before the Lok Sabha.

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

The Government’s response further reveals that another corridor has secured possession of only 7.8 acres against the total requirement of 57 acres, leaving a substantial portion of the required land yet to be acquired.

Status of the Four Corridors

CorridorRouteCurrent Status
Corridor-1
(Sampige)
KSR Bengaluru City –
Devanahalli (41.4 km)
Alignment approved; land acquisition and utility shifting under way
Corridor-2
(Mallige)
Baiyappanahalli –
Chikkabanavara (25.01 km)
Land acquisition completed; station works in progress; tenders invited for remaining works
Corridor-3
(Parijjaata)
Kengeri – Whitefield (35.52
km)
Alignment approved; land acquisition and utility shifting under way
Corridor-4
(Kanaka)
Heelalige – Rajankunte (46.25
km)
Only 7.8 acres acquired out of 57 acres required; station works commenced on available land

Union Government’s Position on Delay in BSRP

The Union Government has attributed the delay in implementation of the Bengaluru Suburban Rail Project (BSRP) primarily to the non-acquisition of private land and the pending transfer of State Government land by the Government of Karnataka. These land-related issues have been identified as key impediments to the timely execution and progress of the project.

In order to address the aforesaid impediments and facilitate expeditious implementation of the project, regular meetings and consultations are being held between K-RIDE and the Ministry of Railways to resolve issues.

Despite the prolonged pendency of these matters, the Union Government has not stipulated any revised completion schedule or fresh deadline for the project. The response instead indicates that further progress remains dependent upon resolution of the outstanding land acquisition and land transfer issues through coordination between the concerned authorities. This rolling stock deal will definitely push the project forward, but the unresolved issues must be addressed in order to ensure the timely completion of the Bengaluru Suburban Rail Project. 

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here