Home Latest News L&T Records 3rd TBM Breakthrough for Patna Metro’s Package PC-03 

L&T Records 3rd TBM Breakthrough for Patna Metro’s Package PC-03 

L&T Records 3rd TBM Breakthrough for Patna Metro’s Package PC-03 
Listen to this story
0:00

Patna ( Metro Rail News): Patna Metro Phase 1 progressed as Larsen & Toubro ( L&T) TBM achieved Tunnel Breakthrough at Patna Junction Shaft. This was the 3rd TBM breakthrough achieved for Package PC-03 by L&T. 

1741756317823

As per the Press Release, Hon’ble Chief Minister of Bihar Sh. Nitish Kumar and the Hon’ble Minister for Urban Development and Housing, Government of Bihar, Sh. Jibesh Kumar and DMRC’s managing director, Dr. Vikas Kumar, were present on the occasion.

1741756319857
1741756317040

About TBM 

The TBM is a 6.65-meter-diameter Earth Pressure Balance (EPB) machine, manufactured by China Railway Construction Heavy Industry Co. Ltd. (CRCHI). It successfully passed factory acceptance tests in the spring of 2023 and was subsequently delivered to Patna in July.

For its first Assignment, TBM  constructed a 1.7 km tunnel between  Gandhi Maidan and Patna Junction Shaft. 

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Package PC-03

In December 2021, L&T grabbed 8 km Package PC-03 from Delhi Metro Rail Corporation (DMRC) at Rs.1989 crores with a 42-month deadline. 

The scope of work under this package includes the construction of twin tunnels between Rajendra Nagar and Patna Junction Railway Station through 6 underground stations. 

Breakthrough Achieved so Far for Package PC-03

Breakthrough TBM Section Distance 
Current Breakthrough TBM Gandhi Maidan–  Patna Junction Shaft. 1.7 km 
First BreakthroughTBM Mahavir (DZ1090) Moin-ul-Haq Station -Patna University Station. ( Downline ) 1494m
Second Breakthrough TBM Buddha (DZ1091) Moin-ul-Haq Station -Patna University Station. ( up-line ) 1494m
ChatGPT Image Jul 30 2026 11 05 29 AMRead nextDMRC Floats Patna Metro Tender for Electrical and Mechanical Systems at Corridor 2 Underground Stations29 Oct 2026

Add Metro Rail News as a preferred source on Google

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.