Mumbai Metro: MMRDA Targets Year-End Opening of Four More Line 9 Stations and Next Line 2B Stretch

Mumbai Metro: MMRDA Targets Year-End Opening of Four More Line 9 Stations and Next Line 2B Stretch
Listen to this story
0:00

MUMBAI (Metro Rail News): The Mumbai Metropolitan Region Development Authority (MMRDA) is targeting the opening of more stations on Metro Line 9 and Metro Line 2B by the end of the year, adding four stations in Mira-Bhayandar and extending service on the eastern suburbs corridor.

Line 9 Phase 2: Four Stations

The second phase of Line 9, from Kashigaon to Subhash Chandra Bose Stadium, will add four stations: Sai Baba Nagar, Meditya Nagar, Shaheed Bhagat Singh Garden and Subhash Chandra Bose Stadium. MMRDA has said civil works on the extension are 96 per cent complete, and the stretch is expected to be completed in December, according to reports citing the Times of India. It is expected to benefit commuters in Mira-Bhayandar.

The first phase of Line 9, a stretch of about 5 km with four stations from Dahisar East to Kashigaon, opened to passengers in April 2026. Line 9 extends Metro Line 7, which runs from Dahisar East to Gundavali in Andheri East, giving Mira-Bhayandar a direct metro link to the western suburbs.

Line 2B: Next Phase After Chembur-Mandale

Line 2B will eventually connect DN Nagar in Andheri West with Mandale in the eastern suburbs. Its first stretch of about 5 km, between Chembur and Mandale, opened in April 2026. The next phase will bring more stations into service, though MMRDA has not yet named them or set a date.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Both openings will need clearance from the Commissioner of Metro Rail Safety (CMRS) before passenger services can start.

Frequently Asked Questions

When will Mumbai Metro Line 9 Phase 2 open?

MMRDA is targeting December 2026, with civil works 96 per cent complete. Passenger services can start only after the Commissioner of Metro Rail Safety (CMRS) inspects and clears the stretch.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Which stations are in Mumbai Metro Line 9 Phase 2?

Sai Baba Nagar, Meditya Nagar, Shaheed Bhagat Singh Garden and Subhash Chandra Bose Stadium.

Which part of Mumbai Metro Line 2B is already open?

The first stretch of about 5 km between Chembur and Mandale, which opened in April 2026.

Also Read: Mumbai Metro Line 12A Gets 3.5 year deadline; CM Fadnavis Targets 2027 as ‘Year of Metro’

HVoaO5SbAAA7GZuRead nextMumbai Metro Line 12A Gets 3.5 year deadline; CM Fadnavis Targets 2027 as ‘Year of Metro’  28 Oct 2026

Add Metro Rail News as a preferred source on Google

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here