Mumbai Metro Line 2B

Operational Operator: MMRDA Length: 23.643 km Since: 08/04/2026 Updated: Official site ↗

Mumbai Metro Line 2B is a 23.643 km elevated line with 20 stations, planned from ESIC Nagar near D.N. Nagar in Andheri West to Mandale in Mankhurd, via Bandra, BKC, Kurla and Chembur. MMRDA is building it. As of October 2026 it is partly open: Mandale to Diamond Garden, 5.4 km and five stations, since 8 April 2026, with Chembur station added on 13 August 2026.

Why it matters

Line 2B is planned as an east-west link across the suburbs, joining the Harbour line belt at Mankhurd and Chembur with Kurla, the BKC business district and Bandra, and meeting Line 2A at D.N. Nagar. The open eastern stretch already connects Metro, suburban rail and Monorail at Chembur. Its Mandale depot, about 28 hectares, is described as Mumbai's largest. Ridership will stay modest until the line reaches Kurla and BKC.

Key facts

  • Operator: MMRDA
  • Length: 23.643 km, 20 stations
  • Status (October 2026): Partially operational (October 2026). Mandale to Diamond Garden (5 stations) open since 8 April 2026; Chembur station added 13 August 2026, giving 6 stations in service. The section from Chembur west to D.N. Nagar is under construction.
  • Cost: ₹10,986 crore (state cabinet approval, September 2016)
  • Trains: BEML, 6-car trainsets, driverless-capable; maintained at Mandale depot

Mumbai Metro Line 2B stations

The 20 stations below run from ESIC Nagar to Mandale. Interchanges are listed where a station connects with another line or a railway station.

#StationTypeConnects to
1ESIC NagarElevated
2Prem NagarElevated
3Indira NagarElevated
4Nanavati HospitalElevated
5Khira NagarElevated
6Saraswat NagarElevated
7National CollegeElevated
8Bandra MetroElevatedBandra railway station (Western line)
9Income Tax OfficeElevatedLine 3 (Aqua), BKC
10ILFSElevated
11MTNL MetroElevated
12S.G. Barve MargElevated
13Kurla (East)Elevated
14Eastern Express HighwayElevated
15ChemburElevatedChembur railway station (Harbour line) / Mumbai Monorail (V.N. Purav Marg)
16Diamond GardenElevated
17Shivaji ChowkElevated
18BSNL MetroElevated
19MankhurdElevatedMankhurd railway station (Harbour line)
20MandaleElevated

Sections and opening dates

SectionStationskmStatusOpened or expected
Mandale to Diamond Garden55.4Operational2026-04-08
Diamond Garden to Chembur1Operational2026-08-13
Chembur to ESIC Nagar (D.N. Nagar)14Under constructionno official date announced

Explore more

Official source: mmrda.maharashtra.gov.in

Latest updates

56 tenders tracked →

See all news & updates →

Phases

PhaseLinesStationsLength (km)Status
Mandale to Diamond GardenMandale to Diamond Garden55.4Operational
Diamond Garden to ChemburDiamond Garden to Chembur1Operational
Chembur to ESIC Nagar (D.N. Nagar)Chembur to ESIC Nagar (D.N. Nagar)14Under construction

Milestones

  • Maharashtra cabinet approves the D.N. Nagar to Mandale corridor at ₹10,986 crore
  • Prime Minister Narendra Modi lays the foundation stone
  • Civil construction begins
  • MMRDA terminates the original civil contracts (Simplex; RCC Infra-MBZ), slowing work
  • Trial runs begin on the Mandale to Diamond Garden stretch
  • Mandale to Diamond Garden section inaugurated by Chief Minister Devendra Fadnavis
  • Passenger service begins on five stations, Mandale to Diamond Garden
  • Chembur station opens after CMRS approval in June 2026

Frequently asked questions

Is Mumbai Metro Line 2B open?

Partly. The Mandale to Diamond Garden section opened to passengers on 8 April 2026 and Chembur station opened on 13 August 2026, so six stations are in service as of October 2026.

Which Line 2B stations are open?

Mandale, Mankhurd, BSNL Metro, Shivaji Chowk, Diamond Garden and Chembur.

How long is Line 2B and how many stations will it have?

The full corridor from D.N. Nagar to Mandale is 23.643 km and elevated, with 20 stations planned.

Where can I change to other lines?

At Chembur you can change to the suburban railway (Harbour line) and the Mumbai Monorail. When complete, the line will also meet Line 3 at BKC and the Western line at Bandra.

When will the full line open?

MMRDA has not announced an official date for the section west of Chembur as of October 2026.

What does Line 2B cost?

The Maharashtra cabinet approved the corridor in September 2016 at ₹10,986 crore.

Who supplies the trains?

BEML supplies the six-car trains, which are maintained at the Mandale depot.

Journey Planner & Route Map

Awarded tenders & contracts

No awarded tenders or contracts recorded yet.

Ongoing tenders

TenderAgencyValueBid dueStatus
MahaMetro invites maintenance tender for Navi Mumbai Metro Line-1 Maha MetroOpen
MRVC invites bids for electrification work in Borivali-Virar Section of Western RailwaysMRVCSubscribersUnder evaluation
Maha Metro floats Rs 3.54 cr tender for Navi Mumbai Metro Line 1 maintenanceMaha MetroSubscribersSubscribersUnder evaluation