MUMBAI (Metro Rail News): Mumbai Metropolitan Region Development Authority (MMRDA) unveiled the five bidders for the architectural finishing and PEB work on Mumbai Metro Line 4.
Scope of the Project
Architectural finishing and plumbing works, including interior fit-outs, facade, etc., along with part design, fabrication, supply and erection of Pre-engineered structures, including entry-exit structures.
Stations
It’s a fully elevated section falling into the CA-194. It’s a 6.94 Km stretch with seven stations: Mulund Fire Station, Mulund Naka, Teen Haath Naka (Thane), RTO Thane, Mahapalika Marg, Cadbury Junction and Majiwada.
Bids Invited
It’s a 6.94 Km package estimated for Rs 198.19 Crore with a deadline of 20 months. The Bids for the same were invited in October 2023.
Bidders
The five bidders for the contract are:
- Eagle Infra India Ltd
- Godrej and Boyce Mfg. Co. Ltd.
- Landmark Corporation Pvt Ltd.
- Relcon Infraprojects Ltd.
- Tata Projects Ltd.
Further Developments
The bids have been sent for further technical evaluation, which can take a couple of months or so to culminate. Once done, the bids will be opened to reveal the lowest bidders and most likely contractors.
Metro Line 4
It is Mumbai’s rapid transit metro line. It is a 32.3 Km long metro line connecting Wadala (Mumbai) to Kasarvadavali via Chembur, Bhandup, Mulund & Teen Hath Naka. It is being built at an estimated cost of Rs 14,549 Crore.
It is expected to increase connectivity to Commercial, government bodies & geographical landmarks in Mumbai. It will reduce the current travel time by 50%-70%. The contract for the Rolling Stock was cancelled in March 2022 owing to the uncertainties of the project.
Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.