Mumbai Metro Line 4

Under Construction Operator: MMRDA Length: 32.32 km Updated: Official site ↗

Mumbai Metro Line 4 is a 32.32 km elevated metro line planned with 32 stations from Bhakti Park in Wadala to Kasarvadavali on Ghodbunder Road, Thane, via Ghatkopar, Vikhroli, Bhandup and Mulund. MMRDA is building it. As of October 2026 no section is open: the first stretch, about 10.5 km from Gaimukh on Line 4A to Cadbury Junction, is on trial runs and awaits CMRS clearance.

Why it matters

Line 4 runs along the Eastern Express Highway and LBS Marg, the main road corridor between the island city's eastern suburbs and Thane, and will be Thane's first metro. With the Line 4A extension to Gaimukh it forms a corridor of about 35 km. It is planned to meet Lines 2B, 5 and 6 and the Monorail, linking Thane to the wider network. Repeated delays to the first section make its opening a closely watched milestone.

Key facts

  • Operator: MMRDA
  • Length: 32.32 km, 32 stations
  • Status (October 2026): Under construction (October 2026). No section is open to passengers. The first stretch, Gaimukh (Line 4A) to Cadbury Junction, about 10.5 km and 10 stations, is on trial runs; RDSO certification came on 2 June 2026 and final CMRS clearance is pending. MMRDA targets late 2026 for it and 2027 for the rest to Wadala.
  • Cost: ₹14,549 crore (state cabinet approval, September 2016); ₹15,498 crore with the Line 4A extension
  • Trains: Alstom Metropolis, 39 six-car driverless trainsets for Lines 4 and 4A, supplied through L&T's integrated systems contract; depot at Mogharpada, Thane

Mumbai Metro Line 4 stations

The 32 stations below run from Kasarvadavali to Bhakti Park (Wadala). Interchanges are listed where a station connects with another line or a railway station.

#StationTypeConnects to
1KasarvadavaliElevatedLine 4A (Green) to Gaimukh
2Vijay GardenElevated
3DongripadaElevated
4Tikuji-ni-wadiElevated
5ManpadaElevated
6KapurbawdiElevatedLine 5 (Orange), under construction
7MajiwadaElevated
8Cadbury JunctionElevated
9Mahapalika MargElevated
10RTO ThaneElevated
11Teen Haath NakaElevated
12Mulund NakaElevated
13Mulund Fire StationElevated
14SonapurElevated
15ShangrilaElevated
16BhandupElevated
17Bhandup MahapalikaElevated
18Naval HousingElevated
19Gandhi Nagar (Kanjurmarg)ElevatedLine 6 (Pink), under construction
20Surya NagarElevated
21VikhroliElevated
22Godrej CompanyElevated
23Shreyas CinemaElevated
24Laxmi NagarElevated
25Pant NagarElevated
26Garodia NagarElevated
27Amar Mahal JunctionElevated
28Siddharth ColonyElevatedLine 2B (Yellow), planned
29Suman NagarElevated
30Anik Nagar Bus DepotElevated
31Wadala Truck TerminalElevated
32Bhakti Park (Wadala)ElevatedMumbai Monorail (Bhakti Park)

Sections and opening dates

SectionStationskmStatusOpened or expected
Gaimukh (Line 4A) to Cadbury Junction1010.5Trial runs; RDSO certification 2 June 2026; CMRS clearance pendingexpected late 2026 (MMRDA target, around Diwali to December)
Cadbury Junction to Bhakti Park (Wadala)24Under constructionexpected 2027

Explore more

Official source: mmrda.maharashtra.gov.in

Latest updates

56 tenders tracked →

See all news & updates →

Phases

PhaseLinesStationsLength (km)Status
Gaimukh (Line 4A) to Cadbury JunctionGaimukh (Line 4A) to Cadbury Junction1010.5Trial runs; RDSO certification 2 June 2026; CMRS clearance pending
Cadbury Junction to Bhakti Park (Wadala)Cadbury Junction to Bhakti Park (Wadala)24Under construction

Milestones

  • Maharashtra cabinet approves the 32 km Wadala to Kasarvadavali corridor at ₹14,549 crore
  • Prime Minister Narendra Modi lays the foundation stone
  • Civil contracts awarded, including Reliance Infrastructure-Astaldi packages
  • Chief Minister Devendra Fadnavis flags off the first trial run on the 4.4 km Gaimukh to Vijay Garden stretch
  • Fatal parapet slab collapse at Mulund delays pre-commissioning work by about two months
  • RDSO certification received for the first phase
  • CMRS inspects the Gaimukh pit-line facility; safety report awaited
  • Alstom rolls out the first of 39 driverless Metropolis trainsets for Lines 4 and 4A at Sri City

Frequently asked questions

Is Mumbai Metro Line 4 open?

No. As of October 2026 no section carries passengers. The first stretch from Gaimukh to Cadbury Junction is on trial runs and awaits final CMRS clearance.

When will the first section open?

MMRDA is targeting late 2026 for the Gaimukh to Cadbury Junction stretch, subject to safety approvals. No firm date has been announced.

How long is Line 4 and how many stations does it have?

Line 4 is 32.32 km long and fully elevated, with 32 stations from Wadala to Kasarvadavali.

What is the difference between Line 4 and Line 4A?

Line 4 runs from Wadala to Kasarvadavali. Line 4A is a short extension of about 2.9 km from Kasarvadavali to Gaimukh, built and operated as one corridor with Line 4.

Which trains will run on Line 4?

Alstom Metropolis driverless trains, 39 six-car sets for Lines 4 and 4A, supplied through L&T. The depot is at Mogharpada in Thane.

How much does Line 4 cost?

The state cabinet approved it in 2016 at ₹14,549 crore; with Line 4A the combined figure is ₹15,498 crore.

Where will Line 4 connect with other lines?

Planned interchanges include Line 5 at Kapurbawdi, Line 6 at Gandhi Nagar (Kanjurmarg) and the Monorail at Bhakti Park, Wadala.

Journey Planner & Route Map

Awarded tenders & contracts

No awarded tenders or contracts recorded yet.

Ongoing tenders

TenderAgencyValueBid dueStatus
MahaMetro invites maintenance tender for Navi Mumbai Metro Line-1 Maha MetroOpen
MRVC invites bids for electrification work in Borivali-Virar Section of Western RailwaysMRVCSubscribersUnder evaluation
Maha Metro floats Rs 3.54 cr tender for Navi Mumbai Metro Line 1 maintenanceMaha MetroSubscribersSubscribersUnder evaluation

Upcoming tenders

No upcoming tenders announced yet.

Bid values, closing dates and awardees are for subscribers. See plans.