KOCHI (Metro Rail News): Kochi Metro Rail Limited (KMRL) will make Jawaharlal Nehru (JLN) Stadium station the main interchange between its Blue and Pink lines when the 11.2-km Phase 2 corridor opens in August 2027. Passengers travelling between Infopark, Kakkanad, Aluva and other destinations on the existing network will have to change trains at the station.
Initially, Pink Line services will terminate at JLN Stadium, with no direct trains from Infopark to Blue Line destinations. However, commuters will be able to travel across both corridors using a single ticket.
Kochi Metro’s JLN Stadium to handle passenger transfers
Under the initial operating plan, passengers travelling between Kochi Metro Phase 1 and Phase 2 will need to switch trains at JLN Stadium. For example, commuters travelling from Infopark to Aluva or Tripunithura will board a Pink Line train to JLN Stadium and transfer to a Blue Line service. KMRL has planned the platforms to simplify passenger movement:
- Platform 1: Trains departing towards Infopark and Aluva.
- Platform 2: Trains arriving from Infopark and Aluva.
A senior KMRL official said the Pink Line will operate at an average speed equivalent to around two minutes per kilometre. The journey from JLN Stadium to Civil Station is expected to take 12 minutes, while travel to Infopark will take around 22 minutes.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
Direct services may be introduced later
KMRL has kept open the option of running direct trains from Infopark onto the Kochi Metro’s Blue Line as passenger numbers increase. According to the official, the corporation could use the existing turnaround tracks at Maharaja’s College or Kadavanthra stations to extend services without requiring a separate operational arrangement. For now, however, passengers will need to change trains at JLN Stadium.
Fleet to be divided between 2 lines
Kochi Metro’s Pink Line will follow the same regular service frequency as the Blue Line. Until additional trains arrive, KMRL plans to distribute its existing fleet of 25 trains between the two corridors. The proposed allocation is:
- Blue Line: 17 trains
- Pink Line: 8 trains
KMRL plans to procure eight additional trains at an estimated cost of ₹275 crore. This would increase the fleet from 25 to 33 trains. However, the procurement remains on hold as the Kerala and Union governments work towards finalising funding approvals. Possible financial support from the Asian Infrastructure Investment Bank is also under consideration.
Track design includes elevated crossing near Palarivattom
The Pink Line will use a track arrangement inspired by the Chennai Metro. After leaving JLN Stadium, its tracks will run parallel to the existing Blue Line of Kochi Metro on either side. At Kurishupally in Palarivattom, the track towards Infopark will rise above the Aluva-bound line before turning towards Kakkanad.
This arrangement will allow the two corridors to connect while maintaining their respective routes. Construction is progressing, with land acquisition near Palarivattom and Padamughal already completed.
August 2027 opening to expand Kochi Metro network
The 11.2-km Pink Line will extend metro connectivity towards Kakkanad and Infopark, while JLN Stadium will serve as the transfer point for passengers connecting to the existing network.
The initial interchange-based operation will require passengers to change trains, but Kochi Metro may consider direct services later as ridership grows and additional trains become available.