GUJARAT (Metro Rail News): The Mumbai-Ahmedabad Bullet Train project has achieved another electrification milestone with the energisation of the overhead equipment (OHE) system on the 50-km Surat-Bilimora section. The development marks progress towards testing activities as the project moves closer to its planned trial runs in 2027.
The National High Speed Rail Corporation Limited (NHSRCL) energised the OHE system on November 20, covering both Up and Down lines along the elevated section. The process will continue in smaller sections under technical supervision to ensure compliance with safety procedures.
2 × 25 kV Traction System to Power Bullet Trains
The 508-km Mumbai-Ahmedabad High Speed Rail corridor uses a 2 × 25 kV overhead traction system, a technology designed to meet the power requirements of high-speed trains. The electrification network will draw power from the national grid through 14 traction substations (TSS) located along the bullet train corridor. These substations will supply electricity to the overhead wires that power the trains.

(Representational image of a bullet train on the Mumbai-Ahmedabad High-Speed Rail Corridor.)
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
The first traction substation at Bilimora, in Gujarat’s Navsari district, has completed installation work across its key buildings. These include facilities for control panels, changeover switches, transformers and circuit breakers. The Bilimora substation will receive power from the 220 kV Ambetha Grid Substation operated by Gujarat Energy Transmission Corporation Limited (GETCO). A centralised control centre will monitor the electrical network to support safe and reliable operations.
Surat-Bilimora bullet train section includes 4 river crossings
The 50-km Surat-Bilimora bullet train stretch runs on an elevated alignment and includes several major structures. Key features include:
- Bridges across four rivers.
- A steel bridge over National Highway 53 (NH-53).
- Around 94,000 noise barriers installed along the viaduct to reduce noise impact on nearby areas.
- Overhead electrical equipment covering both Up and Down tracks.
The energisation of the OHE system adds to the infrastructure readiness of this section and will support further electrical and system testing.
Public safety advisory issued after energisation
With the overhead electrical system now live, NHSRCL has cautioned residents, commuters, construction workers and others near the alignment against approaching or touching the electrical installations. The public has also been advised against carrying out any unauthorised work near the overhead equipment. The warning is particularly important as the system carries high-voltage electricity.
Progress towards 2027 trial runs
The energisation of the Surat-Bilimora section marks an important step in preparing the corridor for subsequent testing. Further sections will undergo energisation in stages, followed by the testing and commissioning activities required before high-speed train trials. The milestone brings the project closer to its next phase, as work continues to prepare India’s first bullet train corridor for trial operations.