Home Chennai Metro Rail Limited (CMRL) Chennai Metro Completes U-Girder Erection on 14.5-km Phase II Corridor 5 Stretch

Chennai Metro Completes U-Girder Erection on 14.5-km Phase II Corridor 5 Stretch

3 min read
0
6
Chennai Metro Completes U-Girder Erection on 14.5-km Phase II Corridor 5 Stretch
Chennai Metro Rail has completed erection of all 911 U-girders on the 14.5 km Koyambedu Market-Alandur stretch.
Listen to this story
0:00

CHENNAI (Metro Rail News): Chennai Metro Rail Limited (CMRL) has completed the erection of all 911 U-girders along the 14.5-km elevated stretch between Koyambedu Market and Alandur under Phase II Corridor 5. The milestone clears a major structural activity on this section, with the final girder installed on November 22, 2026, near Paul Wells Road.

The last U-girder was erected between Butt Road and Kathipara using two hydraulic cranes, each with a lifting capacity of 550 metric tonnes (MT). The work marks the completion of girder erection along the entire Koyambedu Market-Alandur viaduct stretch.

911 U-Girders installed along the Chennai Metro Phase II

The completed section includes 911 precast U-girders, with lengths ranging from 15 metres to 33.33 metres. Each girder weighs around 135 MT on average. Chennai Metro Rail used different erection methods depending on site conditions. These included launching girders and high-capacity hydraulic cranes.

4e285a15 3ae6 4609 a44b 8de4568d0a30
Chennai Metro completes U-girder erection on Phase II Corridor 5.

The work involved several constraints due to the corridor’s location in densely developed parts of the city. Heavy traffic, underground and overhead utilities, limited working space and difficult site conditions made girder installation challenging at multiple locations.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Space constraints required specialised crane arrangements

The project team faced particularly difficult conditions at Kaliamman Koil Street, Butt Road and Paul Wells Road. The integrated flyover along Mount Poonamallee Road added another layer of complexity to the construction work.

At the Upline Span P399-P400, the available space did not allow the two 550-MT cranes to operate in a conventional arrangement. The team adopted an alternative positioning plan, placing one crane inside church premises and the other in a narrow adjoining street.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Workers coordinated the lifting and rigging operations through walkie-talkies to manage the restricted work area.

1,000-MT crane used near school campus

Another major challenge arose at Span P380-P381 on Paul Wells Road. A school and nearby residential buildings left little room to position cranes along the viaduct alignment. To address the problem, the team temporarily used part of the school campus for crane positioning and girder launching. The arrangement required the removal of a section of the school compound wall and connecting passages between buildings.

The work was initially planned during the Vijayadashami holidays, with the affected structures to be restored before the school reopened. This left the construction team with a limited execution window. The available 550-MT cranes could not meet the lifting requirements at the required radius. Chennai Metro Rail therefore mobilised a specialised 1,000-MT crane for the operation.

Major structural milestone for Chennai Metro Phase II Corridor 5

The completion of U-girder erection marks a significant step in the construction of the elevated section between Koyambedu Market and Alandur. The work required coordination among construction teams, utility agencies and other stakeholders, along with traffic management, road diversions and timely mobilisation of equipment.

With all 911 girders now in place, Chennai Metro Rail has completed a major structural milestone on this 14.5-km stretch. The project can now progress towards the remaining construction and systems-related works required before the section becomes operational.

Also Read: Chennai Metro Yellow Line Services to Start at 7 AM Instead of 6 AM From 24 November for Testing Work

chennai metro jpgRead nextCMRL Floats ₹45.79 Cr Tender for Architectural Works at Chennai Metro Phase II Corridor 4 Elevated Stations17 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here