
BHOPAL (Metro Rail News): Bhopal Metro’s first underground stretch is set to miss its November-end deadline, after its original target of 31 May had already slipped, with tunnelling still incomplete, The Times of India reported.
Madhya Pradesh Metro Rail Corporation Limited (MPMRCL) Managing Director S Krishna Chaitanya had last month set the end of November as the deadline for the 500-metre stretch connecting Bhopal railway station with Pul Bogda, near the Subhash Nagar depot.
Bhopal Metro underground work: why it is late
- Ground conditions: Slow excavation and frequent stoppages for grouting and safety work; tunnel boring machine (TBM) speeds have had to be adjusted.
- Soil and water: Engineers had flagged soil conditions and water ingress as challenges in March.
- Progress in June: The first TBM, launched in early April, had advanced 94.5 metres and the second about 20 metres. These were the figures at the time, not the current position.
- Drainage and traffic: Waterlogging near Nadra Bus Stand and diversions around Hamidia Road have added to the difficulty.

Package BH-04 and the second underground stretch
| Information | Details |
| Package | BH-04, twin tunnels under the Hamidia Road area |
| Length | 3.39 km |
| Contractor | KPIL-Gulermak JV (₹769 crore) |
| First stretch | Bhopal railway station-Pul Bogda, 500 m; November deadline at risk |
| Second stretch | Nadra Bus Stand-Sindhi Colony; work limited to station construction so far |
| Orange Line Phase 2 target | End of 2028 |
The second stretch has also drawn local objections, including to the proposed alignment beneath Berasia Road from Nadra Bus Stand.

Why it matters
The underground section carries the Orange Line through the old city to Bhopal railway station, one of its busiest stops. MPMRCL has said the full Orange and Blue Line network is expected by 2028, a target that depends on these tunnels. More on the project is on our Bhopal Metro project page and the MPMRCL website.
Also Read: Bhopal Metro: Otis Emerges L1 for ₹125.85 Cr Lifts, Escalators and Moving Walks Package BH-12
Read nextMumbai Metro Line 3: BMC Drops Underground Passage Below Mahalaxmi Racecourse, ₹702 Cr Science Centre-Coastal Road Link to Be Redesigned23 Nov 2026Get alerts for big metro and rail stories Openings, trials, fares and approvals. Two or three a day at most; turn them off any time.




