Home Indian Railways Indian Railways strengthens Haldia Port connectivity with 18 projects covering 2,455 km

Indian Railways strengthens Haldia Port connectivity with 18 projects covering 2,455 km

Indian Railways strengthens Haldia Port connectivity with 18 projects covering 2,455 km
Representative image

NEW DELHI (Metro Rail News): Indian Railways is developing 18 projects spanning 2,455 km to improve rail links for freight movement to Haldia Port in West Bengal. The aim is to boost cargo handling and logistics efficiency at one of India’s key eastern ports.

Union Railway Minister Ashwini Vaishnaw shared the details in a written reply to a Rajya Sabha question by MP Biswajit Sinha.

Among these, eight projects worth ₹25,106 crore have been sanctioned, Detailed Project Reports (DPRs) has been completed for another eight projects and two projects are currently under survey for DPR preparation.

The minister noted that after DPR preparation, project sanction needs consultations with state governments and approvals from bodies such as NITI Aayog and the Ministry of Finance. Because the process is continuous, exact timelines cannot be fixed.

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

Total projects for improving the connectivity to Haldia Port

  1. Sanctioned Projects 
ProjectLengthSanctioned amount
Sonnagar-Andal 3rd & 4th Line375km13,606cr
Bhagalpur-Dumka-Rampurhat Doubling177km3,169cr
Santragachi-Kharagpur 4th Line111km2,905cr
Aluabari Road-New Jalpaiguri 3rd & 4th Line57km1,786cr
Sainthia-Pakur 4th Line81km1,569cr
Murarai-Barharwa 3rd Line49km978cr
Chandanpur-Shaktigarh 4th Line43km750cr
Pakur-Gumani 4th Line18km343cr
Total- ₹25,106 crore

Sonnagar-Andal 3rd & 4th line Land acquisition is mostly completed except forest diversion of 28 hectares. Works have been taken up for forest diversion, earthwork, bridges, ROBs, RUBs and station buildings.

  1. DPR Prepared
DPR preparedLength
New Jalpaiguri-Kamakhya 3rd & 4th Line445km
Kharagpur-Jharsuguda (Bagdehi) 4th Line367km
Kharagpur-Bhadrak (Ranitlal) 4th Line173km
Kumedpur-Aluabari 3rd & 4th Line129km
Barharwa-Bhagalpur 3rd & 4th Line128km
Malda Town-Kumedpur 3rd & 4th Line62km
Gumani-Malda 3rd & 4th Line59km
Andal-Sainthia 3rd & 4th Line73km
  1. Survey ongoing
Survey ongoing ProjectLength
Khanna-Sainthia 3rd Line (Final Location Survey sanctioned)84km
Panskura-Tamluk 3rd & 4th Line (Field Survey taken up)24km

In addition to the Haldia Port connectivity works, 1,187 km of other railway projects are currently under execution across West Bengal. The total budget allocation for infrastructure projects and safety works in West Bengal 2026-2027 is ₹14,205 Cr. more than three times compared to 2009-2014, which was ₹4,380 crore per year.

As on April 2026, 63 projects including 14 New Lines, 04 Gauge Conversions and 45 Doubling projects, covering a total length of 5,148 Km, costing ₹83,433 crore, falling fully/partly in West Bengal are sanctioned.

Also Read: Indian Railways loaded freight weighing equivalent to ~2,105 ‘Statue of Unity’ in July 2026