
Table of Contents
Mumbai (Metro Rail News): On 23 July, Leena Powertech Engineers Pvt. Ltd. emerged as the lowest bidder for the 25 Kv AC OHE electrification contract of Line-7A and Line 9 of the Mumbai Metro project.
Mumbai Metro’s Line 7A and Line 9
The construction is underway for both Line 7A and Line 9. Both lines will serve as the extensions of existing operational Line 7 which covers a total distance of 16.5 km from Gundavali to Dahisar East. The details of both Lines 7A and 9 are below:
Line 7A:
This line will extend Line 7 in the southward direction. This extension runs 3.17 km from Gundavali to CSIA. The electrification contractor will equip this line with rigid OHE (ROCS).
Line 9:
This line is the northern extension of Line 7. Line 9 spans 11.38 km from Mira Bhayandar to Dahisar East. The electrification contractor will install flexible OHE (FOCS) on this line.
The weekly brief metro & rail professionals read.
Bidding Process
In June 2023 Mumbai Metropolitan Region Development Authority (MMRDA) called for bids to carry out the electrification work on Line 7A and Line 9 under Package CA-176.
MMRDA’s Expected Cost: 108.01 Crore
Deadline: 30 months
In December 2023, MMRDA opened technical bids and revealed 4 bidders for Package CA-176. During the technical evaluation, the bids placed by BNC Power Projects Ltd. and Texmaco Rail and Engineering Ltd. didn’t meet the terms of the tender; subsequently, their bids were disqualified.
Financial Bids
| Firm | Bid price |
| Leena | 122.09 crore |
| Siemens | 185.35 crore |
Scope of work
The appointed contractor under this electrification contract will be responsible for the design, manufacture, supply, installation, testing, and commissioning of various electrical systems for Metro Line 9 and Line 7A of the Mumbai Metro project.
Key responsibilities include:
- 33 kV and 25 kV Cabling Work
- Cabling work for efficient power transmission.
- 25 kV Overhead Equipment (OHE) System
- Installation of the 25 kV OHE system to power metro trains.
- Switching Station
- Establishing a switching station for managing electrical supply.
- 33 kV Auxiliary Power Distribution System
- Designing and installing the 33 kV auxiliary power system.
- 33/0.415 kV Auxiliary Substation (ASS)
- Setting up substations to step down voltage from 33 kV to 0.415 kV.
- Supervisory Control and Data Acquisition (SCADA) System
- Implementing a SCADA system to monitor and control electrical systems.
Update on Line 7A and Line 9
Line 7A: Currently, Tunneling work is under on this corridor.
Line 9: MMRDA is pursuing superstructure works to facilitate the construction of a Viaduct on corridor 9.



