First OWG Bridge launched for Mumbai-Ahmedabad Bullet Train Project

0
2,618
First OWG Bridge launched for Mumbai-Ahmedabad Bullet Train Project
MAHSR_OWG

This article has not been translated yet, so the English original is shown below. Translate now (takes a few seconds).

VADODARA (Metro Rail News): M. G. Contractors Pvt. Ltd. (MGCPL) accomplished a major achievement in the construction of the Mumbai-Ahmedabad High-Speed Rail (MAHSR) project. They completed the installation of the first open web girder (OWG) truss bridge for Package P1(C) last week. This key infrastructure piece spans the Indian Railways’ main-line track between Kanjari Boriyavi and Uttarsanda stations in the Vadodara division, Gujarat.

The bridge, identified as GAD-31, stretches 99.6 meters in length and was meticulously positioned using a major traffic and power block. Weighing approximately 1486 metric tons, the bridge was engineered with precision to align at a 62-degree skew relative to the crucial railway line linking Delhi and Mumbai. The structure, which stands 14 meters high and extends 14.3 meters wide, was manufactured by the Goodluck India group in Gujarat.

Awarded the bridge package P-1(C) contract by India’s National High Speed Rail Corporation (NHSRCL) in August 2021 for Rs. 261.24 crore, MGCPL’s task includes the construction of one prestressed concrete (PSC) and four steel truss bridges as part of the 87.569 km Package C6, which runs from Vadodara to Ahmedabad and is being constructed by Larsen & Toubro.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

The bridge’s assembly was supported by a trestle erection that began in April 2023, marking a full year of meticulous preparation and construction efforts leading up to this landmark achievement.

In total, an estimated 70,865 metric tons of steel will be used to fabricate the 28 steel bridges along the line. The installation of the first OWG at MAHSR’s chainage 254.585 over NH-53 near Surat, completed in October 2023 by MG Contractors, paved the way for this subsequent success.

For ongoing updates and more information on the High-Speed Rail project, be sure to visit the dedicated section on our website. Readers can also sign up for free email notifications for new posts and gain early access to updates by supporting the site.

Project Overview

High-Speed Rail in India – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here