Agra (Metro Rail News): Recently, the Agra Metro Phase 1 project witnessed 2 milestones on Line 1 when Afcons-Sam India Consortium’s TBM Ganga and TBM Shivaji achieved breakthroughs at SN Medical College Station and Raja Ki Mandi, respectively.
TBM 324 and TBM S718C established the 13th and 14th breakthroughs for the 7.93 km underground Package AGCC-02 of Agra Metro Phase 1.
TBM Ganga’s Journey in Agra Metro Phase 1
TBM Ganga, also known as TBM 324, is the 2nd TBM deployed for the Agra Metro Project.
TBM Ganga’s journey so far records the construction of;
First Assignment | Ramleela Maidan – Agra Fort Station | 334m | June 2023 |
---|---|---|---|
Second Assignment | Agra Fort Station – Shahjahan Gardens Midshaft | 175m | September 2023 |
Third Assignment | Shahjahan Gardens Midshaft – Taj Mahal Station | 1175m | December 2023 |
Current Assignment | Agra College Station – SN Medical College Station. | 525m | August 2024 |
TBM Shivaji’s Journey in Agra Metro Phase 1
TBM Shivaji, nicknamed TBM S-718C, is the 3rd TBM machine deployed for the Agra Metro Project.
TBM Shivaji’s journey so far records the construction of;
First assignment | Taj Mahal Station -Taj Mahal Ramp | 228m | October 2023 |
Second Assignment | RBS Ramp -RBS College Station. | 734m | December 2023 |
Current Assignment | RBC College- Raja Ki Mandi Station. | 685m | August 2024 |
Package AGCC-02
In March 2022, Afcons – Sam India Consortium bagged Rs. 1819.79 crore underground Package AGCC-02 with a 48-month deadline.
The scope of work under this package includes the construction of twin tunnels connecting 7 stations at;
- Taj Mahal
- Agra Fort
- Jama Masjid
- SN Medical College
- Agra College
- Raja Ki Mandi
- RBS College
Upcoming Developments
Till date,14 breakthroughs have been achieved out of 18 breakthroughs planned for the Agra Metro Phase 1 project.
In future, The remaining breakthroughs will be recorded at:
- 2 breakthroughs at Agra College
- 2 breakthrough at Mankameshwar (Jama Masjid)