VISAKHAPATNAM (Metro Rail News): South Coast Railway (SCoR) is accelerating the redevelopment of Visakhapatnam Railway Station, located at the headquarters of the newly operationalised railway zone. The station modernisation project is among the key infrastructure priorities aimed at improving passenger facilities, increasing train-handling capacity and strengthening railway operations in the region.
SCoR General Manager Sandeep Mathur, while speaking with The Hindu said, that the railway board has authorised ₹300 Crore for remodeling the coaching yard, marking a key moment in this project.
“We are taking utmost care in planning every aspect of the project, including architectural design, integration of facilities, infrastructure expansion and future requirements, with a long-term vision of creating a modern railway station capable of meeting the needs of the people of this region for the next 50 years and beyond,” Mr. Mathur said.
Visakhapatnam railway station upgrade targets 2028 completion
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
This project’s constructural work is estimated at ₹450 crore and spread over 60 acres. This project is going to extend the total number of platforms from 8 to 14 and platform lines to 11 to 16. All new platforms will have ballastless tracks, while existing Platforms 3, 5, and 6 are being widened, also two new G+2 station buildings spanning over 200 metres are going to be connected by a massive 72-metre-wide and 205-metre-long Air Concourse.
This project is targeted to be completed by the end of 2028, efforts are constantly being made to speed up this project without compromising safety, quality and passenger service.
Congestion Relief and Construction Progress
The station currently has eight operational platforms, which can cause traffic congestion amidst peak hours, to access maintenance tracks incoming and outgoing trains have to cross paths and they frequently hit signal bottlenecks. This forces trains to stop on the outskirts for 20 minutes or more while waiting for clearance. Changing the engines of the train is also time consuming because of less space. The redevelopment is being done as an initiative to stop these delays, the extension of 14 platforms is going to stop the waiting time outside and improve movement of trains, also dedicated rail engines are being prepared in case of urgent swaps ensuring smoother operations and faster movement of trains.
Construction work is progressing gradually, while additional spaces are under development, temporary parkings zones on the west (4,000 sq. m) and east (5,860 sq. m) are working. Structural steel to be used for the North Foot bridge has arrived. Excavation for platform walls from platforms 10 to 14 has been completed. First-floor staging for the western building and slab completions at the Passenger Reservation Building has also successfully been completed.