The Delhi Metro Golden Line (Line 10) is a 23.62 km Phase 4 corridor from Delhi Aerocity to Tughlakabad with 15 stations, 11 underground and 4 elevated. As of October 2026 it is under construction, with civil work over 83% complete. DMRC is targeting December 2026 for the first 8.4 km section from Tughlakabad to Sangam Vihar. Fares and timings are not yet announced.
The Golden Line gives south Delhi its first east to west metro link, connecting Tughlakabad and the Mehrauli-Badarpur Road belt with Chhatarpur and the airport district at Aerocity. Interchanges with the Violet, Yellow and Airport Express lines let Faridabad and south-east Delhi riders reach the airport without going through central Delhi. Its 2.4 km double-decker viaduct, with road traffic below and metro above, is a first for DMRC, and later extensions will take the network to 38 km.
The 15 stations below run from Delhi Aerocity to Tughlakabad. Interchanges are listed where a station connects with another line or a railway station.
| # | Station | Type | Connects to |
|---|---|---|---|
| 1 | Delhi Aerocity | Underground | Airport Express Line (Orange) |
| 2 | Mahipalpur | Underground | |
| 3 | Vasant Kunj | Underground | |
| 4 | Kishangarh | Underground | |
| 5 | Chhatarpur | Underground | Yellow Line |
| 6 | Chhatarpur Mandir | Underground | |
| 7 | IGNOU | Underground | |
| 8 | Neb Sarai | Underground | |
| 9 | Saket G Block | Elevated | Golden Line branch to Lajpat Nagar (under construction) |
| 10 | Ambedkar Nagar | Elevated | |
| 11 | Khanpur | Elevated | |
| 12 | Sangam Vihar | Elevated | |
| 13 | Anandmayee Marg Junction | Underground | |
| 14 | Tughlakabad Railway Colony | Underground | |
| 15 | Tughlakabad | Underground | Line 6 (Violet) / Tughlakabad railway station |
| Section | Stations | km | Status | Opened or expected |
|---|---|---|---|---|
| Tughlakabad to Sangam Vihar | 4 | 8.4 | Under construction, first section to open | expected December 2026 (DMRC target) |
| Sangam Vihar to Delhi Aerocity | 11 | 15.2 | Under construction | in phases after December 2026, no date announced |
Official source: www.delhimetrorail.com
| Phase | Lines | Stations | Length (km) | Status |
|---|---|---|---|---|
| Tughlakabad to Sangam Vihar | Tughlakabad to Sangam Vihar | 4 | 8.4 | Under construction, first section to open |
| Sangam Vihar to Delhi Aerocity | Sangam Vihar to Delhi Aerocity | 11 | 15.2 | Under construction |
The main line runs 23.62 km from Delhi Aerocity to Tughlakabad through 15 stations, passing Mahipalpur, Vasant Kunj, Chhatarpur, IGNOU, Saket G Block and Sangam Vihar.
DMRC is targeting December 2026 for the first section, Tughlakabad to Sangam Vihar. The remaining stretch to Aerocity will open in phases after that, and no date has been announced.
The first section has four stations: Tughlakabad, Tughlakabad Railway Colony, Anandmayee Marg Junction (all underground) and Sangam Vihar (elevated).
Interchanges are planned with the Airport Express Line at Aerocity, the Yellow Line at Chhatarpur and the Violet Line at Tughlakabad. Saket G Block will link to the Golden Line branch towards Lajpat Nagar.
DMRC changed the corridor's colour from silver to gold in January 2024. The route itself did not change.
Yes. The Lajpat Nagar to Saket G Block branch is under construction under Phase 4, and Phase 5A extensions to IGI Airport Terminal 1 and Kalindi Kunj were approved in December 2025.
Alstom is supplying 13 six-coach driverless-capable trains, which began arriving at Sarita Vihar depot in April 2026.
No awarded tenders or contracts recorded yet.