Nagpur (Metro Rail News): The joint venture of YFC Projects and BBG Infrastructure has started casting activities for Package C-09 under Phase 2 of the Nagpur Metro project. A brief ceremonial event, including a pooja, was held to mark the initiation, attended by representatives from BBG, project contractors, Nagpur Metro Rail Corporation (NMRC), and General Consultant (GC) teams.

Package C-09 is a part of the 43.8 km Phase 2` of the Nagpur Metro, specifically on the Orange Line’s Reach-1A. The scope includes the construction of eight elevated stations:
Ashokvan
Dongargaon
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.
Mohgaon
Meghdoot CIDCO
Butibori Police Station
MHADA Colony
MIDC KEC
MIDC ESR
Contract Details:
Maharashtra Metro Rail Corporation Limited (Maha-Metro) invited bids for Package C-09 in April 2024, with an estimated contract value of ₹258 crore and a completion timeline of 2.5 years.

In January 2025, the YFC–BBG JV was selected as the lowest bidder, quoting ₹219.33 crore. The project is being financed through a USD 200 million loan secured from the Asian Development Bank (ADB).
Scope Overview:
The primary scope under Package C-09 includes the civil construction of the aforementioned eight elevated metro stations. The associated viaduct works connecting these stations fall under Package C-02, which was awarded to GR Infraprojects Ltd. (GRIL) in October 2024 at a contract value of ₹903.53 crore.
Read nextMaha Metro Identifies L1 Bidder for ₹209 Cr Nagpur Metro Phase 2 Track Contract3 Oct 2026