YFC Projects – BBG JV Commences Casting Work for Package C-09 of Nagpur Metro Phase 2

YFC Projects – BBG JV Commences Casting Work for Package C-09 of Nagpur Metro Phase 2

Nagpur (Metro Rail News): The joint venture of YFC Projects and BBG Infrastructure has started casting activities for Package C-09 under Phase 2 of the Nagpur Metro project. A brief ceremonial event, including a pooja, was held to mark the initiation, attended by representatives from BBG, project contractors, Nagpur Metro Rail Corporation (NMRC), and General Consultant (GC) teams.

02a2e260 5589 444b a8ec 9edd26a125e0 1

Package C-09 is a part of the 43.8 km Phase 2` of the Nagpur Metro, specifically on the Orange Line’s Reach-1A. The scope includes the construction of eight elevated stations:

Ashokvan

Dongargaon

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

Mohgaon

Meghdoot CIDCO

Butibori Police Station

MHADA Colony

MIDC KEC

MIDC ESR

Contract Details:

Maharashtra Metro Rail Corporation Limited (Maha-Metro) invited bids for Package C-09 in April 2024, with an estimated contract value of ₹258 crore and a completion timeline of 2.5 years.

8fd2f17f 27a7 4fea 9aae 1cd80956e2d4

In January 2025, the YFC–BBG JV was selected as the lowest bidder, quoting ₹219.33 crore. The project is being financed through a USD 200 million loan secured from the Asian Development Bank (ADB).

Scope Overview:

The primary scope under Package C-09 includes the civil construction of the aforementioned eight elevated metro stations. The associated viaduct works connecting these stations fall under Package C-02, which was awarded to GR Infraprojects Ltd. (GRIL) in October 2024 at a contract value of ₹903.53 crore.

Project Overview

Nagpur Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here