NEW DELHI (Metro Rail News): National Capital Region Transport Corporation (NCRTC) recently opened technical bids for the 82.15 km Delhi – Meerut RRTS Line‘s Package 12B which revealed that three firms have submitted bids to design, supply and erect pre-engineered steel roof structures at 12 elevated stations.
NCRTC had invited bids for this work in 2 lots in September right after Sam India Builtwell emerged as the lowest bidder for Package 12A for similar roof-work at Package 1 and 2’s Sahibabad, Ghaziabad, Guldhar and Duhai stations.
For Package 12B, 7 of these 12 stations form a part of the 33 km Package 3 (under construction by Larsen & Toubro) – the ones at Murad Nagar, Modi Nagar South, Modi Nagar North, Meerut South, Partapur, Rithani & Shatabdi Nagar.
NCRTC’s combined estimate is $8.71 million (Rs 63.79 crore) and it expect the assigned contractor(s) to complete all civil work in 1358 days.
Bidders:
Galadari Engineering Works Ltd.
Pioneer Fabricators Pvt. Ltd.
URC Construction Pvt. Ltd.
Lot-1: DM/CN/COR-OF/119
Lot-P12B L1: – Design, Fabrication, Supply and Erection of Pre–Engineered Steel Roof Structure of 6 (Six) Elevated stations viz Murad Nagar, Modi Nagar South, Modi Nagar North, Meerut South, MES Colony and Daurli Stations of Delhi – Ghaziabad –Meerut RRTS Corridor.
Lot-2: DM/CN/COR-OF/120
Lot-P12B L2: – Design, Fabrication, Supply and Erection of Pre–Engineered Steel Roof Structure for 6 (Six) Elevated stations viz Partapur, Rithani, Shatabdi Nagar, Brahmpuri, Meerut North and Modipuram of Delhi – Ghaziabad – Meerut RRTS Corridor.