Rishikesh-Karnaprayag Rail Project: MEIL Completes Excavation of Both Main Tunnels Under Package 8

2 min read
0
0
Rishikesh-Karnaprayag Rail Project: MEIL Completes Excavation of Both Main Tunnels Under Package 8
MEIL has completed excavation of both main tunnels, 13.6 km in total, under Package 8 of the Rishikesh-Karnaprayag rail project.(Representational Image)
Listen to this story
0:00

UTTARAKHAND (Metro Rail News): Megha Engineering and Infrastructures Ltd (MEIL) has completed excavation of the 6.593 km main tunnel of Tunnel 14 on the Rishikesh-Karnaprayag railway project in Uttarakhand. The breakthrough, achieved on November 27, completes excavation of both main tunnels under Rail Vikas Nigam Limited’s (RVNL) Package 8, covering a combined length of 13.6 km.

MEIL announced the milestone on X, stating that excavation of Tunnel 14 was carried out through challenging Himalayan geology using the New Austrian Tunnelling Method (NATM). The work involved excavation from both portals and required continuous geological assessment and adjustments to ground-support measures.

Both main tunnels completed under Package 8

Package 8 includes two major tunnels, Tunnel 14 and Tunnel 15. With the latest breakthrough, excavation of both main tunnels, spanning approximately 13.6 km, has been completed. During work on Tunnel 14, construction teams encountered several geological and engineering challenges, including:

  • Complex portal treatment requirements near Marora village.
  • Unexpected underground cavities.
  • Heavy water seepage.
  • Variations in rock formations along the alignment.

MEIL said its teams used controlled blasting, continuous geological monitoring and site-specific ground-support systems to manage these conditions.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

NATM used for Himalayan tunnel excavation

The New Austrian Tunnelling Method (NATM) was used to excavate Tunnel 14. The approach involves monitoring the behaviour of surrounding rock during excavation and adapting support measures to suit ground conditions.

Work progressed simultaneously from both tunnel portals to advance excavation through the difficult terrain. The method required close coordination between engineers, supervisors and workers operating in restricted underground spaces.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Rishikesh-Karnaprayag rail project targets 2029

The Rishikesh-Karnaprayag New Railway Line is an under-construction broad-gauge corridor of approximately 125-126 km in Uttarakhand. RVNL is executing the project, which aims to improve rail connectivity to the Garhwal region. The corridor is targeted for completion by December 2029. Its construction involves extensive tunnelling and bridge works through the challenging Himalayan landscape.

Completion of excavation in both main tunnels under Package 8 marks a significant construction milestone for the railway corridor. The project will now need to progress through subsequent tunnel works, finishing and railway infrastructure installation before it can enter service.

Also Read: Siemens Awarded ₹263 Cr Electrification Contract  for Rishikesh-Karnaprayag Rail Line 

train 18 tracks 1200Read nextJupiter Wagons Forms 80:20 JV with South Korea’s Woojin to Manufacture Metro Trains and Propulsion Systems in India24 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here