New MD Conducts Inspection on the Priority Stretch of the Bhopal Metro

Date:

Share post:

BHOPAL (Metro Rail News): Yesterday, on Friday, 16th February 2024, Shri Sibi Chakraborty IAS assumed the charge of managing director of Madhya Pradesh Metro Rail Corporation (MPMRCL). Concurrently, he conducted a comprehensive review meeting and site inspection concerning the Bhopal Metro Rail Priority Corridor.

Review Meeting 

During the review meeting, the Managing Director engaged with senior officials of the Metro Rail Corporation, along with the General Consultant and contractors, to discuss pertinent matters regarding the Bhopal Metro Priority Corridor. 

Subhash Nagar Metro Station 

Subsequently, MD Shri Chakraborty proceeded to the Subhash Nagar Metro Station site for a firsthand construction progress inspection. He closely observed the ongoing works, expressed satisfaction with the progress made thus far, and issued directives to ensure the timely completion of the remaining tasks under the Priority Corridor.

Bhopal metro Insoection 02

Officials Accompanied 

The inspection program, led by the Managing Director, saw the participation of key officials, including Sh. Ajay Sharma, Director (Project), Sh. Shobhit Tandon, Director (System), Sh. YC Sharma, General Manager (Civil), Sh. Sanjay Singh, General Manager (Civil), Sh. Ajay Gupta, General Manager (Track), Sh.N.D. Shakyawar, General Manager (E&M), Sh. Manish Gangarekar, General Manager (Rolling Stock), officials from the General Consultant and representatives of Metro construction contractors.

Bhopal metro Insoection 03

Bhopal Metro  

Bhopal Metro’s Phase 1 project’s DPR (Detailed Project Report ) with routes of 27.90 km was approved by the state government in December 2016 and by the Central Government’s cabinet in October 2018. It consists of 2 lines: 

01. Line-2 or Orange Line: Karond Circle – AIIMS – 14.99 km

02. Line-5 or Blue Line: Bhadbhada Square – Ratnagiri Tiraha – 12.91 km

Bhopal Metro’s Priority Corridor will be completed and opened in March 2024. 

Bhopal metro Insoection 04

Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Structcon Bags Proof Checking Consultant Contract for Pune Metro’s  PCMC-Nigdi Extension

Pune (Metro Rail News): MahaMetro, or Maharashtra Metro Rail Corporation, appointed  Structcon Design Pvt. Ltd. as a Proof...

From Manual To Automatic: The Impact Of Train Technology In Indian Railways

One of the largest and oldest rail networks in the world, the Indian Railways was established in 1853....

Trial Run Started On Bengaluru Metro’s Yellow Line

Bengaluru (Metro Rail News):The long-awaited Bengaluru Metro’s Yellow Line has reached another milestone, with the start of Oscillation...

Coimbatore Suburban Railways: Reinforcing Local Connectivity

Taking A Trip To CoimbatoreOverview of Coimbatore Suburban RailwaysRoutes of Coimbatore Suburban RailwaysCoimbatore Jn – MettupalayamCoimbatore Jn. –...