Nagpur Metro: 5 Firms Submit Proposal for Phase2’s OHE Contract

Date:

Share post:

Nagpur (Metro Rail News): On June 26, Maharashtra Metro Rail Corporation Ltd. (Maha-Metro) opened the technical bids for package TR-02. Five firms have submitted proposals to undertake the overhead equipment (OHE) electrification work for the 43.8 km Phase 2 of Nagpur Metro.

The Asian Development Bank (ADB) and the European Investment Bank (EIB) will fund Package TR-02 through a proposed loan.

Nagpur Metro
Nagpur Metro: 5 Firms Submit Proposal for Phase2’s OHE Contract 2

Scope of work:

Package TR-02 involves a comprehensive scope of work, including the design, supply, installation, testing, and commissioning of a 25kV flexible overhead equipment (OHE) system and sectioning posts for Phase 2 of the Nagpur Metro Rail Project. This infrastructure is crucial for ensuring efficient and reliable electrical distribution along the metro network’s at-grade and elevated sections.

Bidding Process

In December 2023, Maha Metro issued a call for bids for Package TR-02. The tender was released with an undisclosed budget and a completion deadline of 180 weeks (3.45 years).

The firms that have submitted proposals for Package TR-02 include:

  1. Siemens Ltd. – Rail Vikas Nigam Ltd. (RVNL) JV
  2. Kalpataru Projects International Ltd. (KPIL)
  3. Texmaco Rail and Engineering Ltd.
  4.  KEC International Ltd.
  5. Konkan Railway Corporation Ltd

The bids will now undergo a comprehensive technical evaluation process, which probably will take a few months to complete. Following this evaluation, Maha Metro will reveal the financial bids of the technically qualified bidders to identify the L1 (Lowest Bidder) for package TR-02.

Nagpur Metro Phase 2 Project

In January 2019, the Maharashtra government approved the Detailed Project Report (DPR) of the 43.8 km long Nagpur Metro Phase 2 project at Rs.  5,976 crore. However, in  2023, the state cabinet revised the estimated project cost to Rs. 6,708 crore.

Phase II will cover a total distance of 43.8 km through extensions of the existing two corridors. It will incorporate a total of 35 stations. Upon completion, Phase 2 will expand the Nagpur Metro Network to 82 km.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

TBM DZ1041 Records Breakthrough At Sterling Road Station Of Chennai Metro Line 3 

Chennai (Metro Rail News): Another milestone has been recorded in Chennai Metro Phase 2 as Larsen & Toubro...

Patna Metro received bids from 5 firms for an underground contract 

Patna  (Metro Rail News): Recently, 5 firms have submitted bids for the underground construction of  30.91 km long...

Bangalore Metro Yellow Line To Start Operations In January 2025 

Bangalore (Metro Rail News): Bangalore Metro Rail Corporation Limited( BMRCL) announced on 5 October that the commencement of...

2 Firms Qualify For DDC-03 Contract Of Pune Metro’s Aqua Line Extension 

Pune (Metro Rail News): Two Firms, SYSTRA MVA Consulting (India) and STUP – RITES JV have qualified for...