NEW DELHI (Metro Rail News): India’s first bullet train service will start in 2027 on the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor, with the rest of the line to Mumbai opening in phases, Railway Minister Ashwini Vaishnaw said on 20 November.
Writing on Substack, Vaishnaw also said track trials of the indigenous B28 bullet train, being built by Integral Coach Factory (ICF) and BEML, are expected by mid-2027. ANI reported that the first service is due in the last quarter of 2027.
Bullet train progress on the Mumbai-Ahmedabad corridor
| Work | Progress cited by the minister |
| Pier work | 456 km (as of September) |
| Viaduct | 371 km (as of September) |
| Noise barriers | 6 lakh installed along 299 km |
| Overhead equipment (OHE) masts | 9,300 installed across 206 km of viaduct |
| Stations | Civil work complete at 8 stations; architectural finishing under way |
| Mountain tunnels | 4 excavated |
| Maharashtra tunnel (21 km, 7 km under Thane Creek) | 5 km excavated by the mountain tunnelling method; two TBMs launched from Vikhroli and Sawli in July 2026 |
| Depots | Work in progress at Sabarmati, Surat and Thane |
Each of the two tunnel boring machines has a 13.6-metre cutterhead, weighs over 3,000 tonnes and is 96 metres long, Vaishnaw said. India’s first undersea rail tunnel will run beneath Thane Creek.

Indigenous B28 bullet train: what we know
- Builders: ICF and BEML, at BEML’s Bengaluru facility.
- Design speed: 280 km/h. A faster B35 for 350 km/h is the next step.
- Status: The first body frame is complete and undergoing structural testing.
- Train: About 202 metres long, eight coaches (four motor, four trailer) and about 557 seats, with seven standard-class coaches (3×2) and one executive coach (2×2), according to ANI. Two trainsets can be coupled into a 16-coach train.
Vaishnaw added that the main transformers, mast cross-arms and the ground, protection and feeder wires of the electrification system are also being made in India.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Why the bullet train took this long
The project could not start in Maharashtra for about two and a half years because state permissions and land acquisition were pending, and COVID cost two more years, Vaishnaw said. “So, when critics ask, ‘where is the bullet train’, the honest answer is: serious construction is just five years old,” he wrote. Full construction began in 2021.
The 2027 start fits work already under way in Gujarat: the Surat-Bilimora section was energised with 25 kV from 20 November. The project’s cost has risen to about ₹2.02 lakh crore. Follow the full timeline on our Mumbai-Ahmedabad HSR project page and on the NHSRCL website.