Chennai Metro: Six Stations Between Vadapalani and Porur May Open Only by Mid-2027, Await ATO Trials and CMRS Nod

2 min read
0
0
Chennai Metro: Six Stations Between Vadapalani and Porur May Open Only by Mid-2027, Await ATO Trials and CMRS Nod
Porur Bypass station on Chennai Metro Phase 2 Corridor 4. Photo: TamizhanEditor / Wikimedia Commons (CC BY-SA 4.0)
Listen to this story
0:00

CHENNAI (Metro Rail News): Chennai Metro passengers on Arcot Road may have to wait until mid-2027 for six stations between Vadapalani and Porur to open. The stations could be built by early 2027, but services may not start before June, as Chennai Metro Rail Limited (CMRL) first has to complete automated train operation trials on the whole Vadapalani-Poonamallee Bypass stretch, The Times of India reported.

Chennai Metro stations still closed

When the 14.64 km Poonamallee Bypass-Vadapalani stretch of Phase 2 Corridor 4 (Lighthouse-Poonamallee Bypass) opened on 11 October, these six stations stayed shut because construction was not finished. Trains run through them without stopping.

StationStatus
Alapakkam JunctionClosed; trains skip
KarambakkamClosed; trains skip
ValasaravakkamClosed; trains skip
AlwarthirunagarClosed; trains skip
Saligramam WarehouseClosed; trains skip
SaligramamClosed; trains skip

Four of the six are on the double-decker section that carries Corridors 4 and 5 of the 118.9 km Phase 2 one above the other.

Chennai Metro Phase 2 driverless trainset
A Chennai Metro Phase 2 driverless trainset. Photo: TamizhanEditor / Wikimedia Commons (CC BY-SA 4.0)

Why ATO mode decides the opening date

  • Civil work: Entry structures and facades are being built, with completion expected by January or February 2027.
  • Safety clearance: The Commissioner of Metro Railway Safety (CMRS) will inspect the stations, but “will not accept trains being operated in manual mode,” an official said.
  • ATO first: Trains must run at least in Automatic Train Operation (ATO) mode, with an operator on board, before the stations can open.
  • UTO later: “We expect to operate in UTO mode only by June or July 2027,” another official said, referring to unattended train operation.

Civil work slowed after trains began running, especially on the double-decker section, officials said.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Chennai Metro Thelliyaragaram station on Corridor 4
Thelliyaragaram station on the Poonamallee Bypass-Vadapalani stretch. Photo: TamizhanEditor / Wikimedia Commons (CC BY-SA 4.0)

Why it matters

Arcot Road is one of west Chennai’s busiest corridors, and residents there now have to travel to Vadapalani or Porur to board. “If the station in my area opens, it would take barely five minutes to reach it, instead of the 20 minutes I now spend travelling to Vadapalani during peak hours,” said M Shankaran, a Saligramam resident. Follow Corridor 4 on our Chennai Metro Line 4 project page.

Also Read: Chennai Metro to Start 6 AM Services on Poonamallee–Vadapalani Stretch from October 23 

chennai metro jpgRead nextCMRL Floats ₹45.79 Cr Tender for Architectural Works at Chennai Metro Phase II Corridor 4 Elevated Stations17 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here