CHENNAI (Metro Rail News): Chennai Metro passengers on Arcot Road may have to wait until mid-2027 for six stations between Vadapalani and Porur to open. The stations could be built by early 2027, but services may not start before June, as Chennai Metro Rail Limited (CMRL) first has to complete automated train operation trials on the whole Vadapalani-Poonamallee Bypass stretch, The Times of India reported.
Chennai Metro stations still closed
When the 14.64 km Poonamallee Bypass-Vadapalani stretch of Phase 2 Corridor 4 (Lighthouse-Poonamallee Bypass) opened on 11 October, these six stations stayed shut because construction was not finished. Trains run through them without stopping.
| Station | Status |
| Alapakkam Junction | Closed; trains skip |
| Karambakkam | Closed; trains skip |
| Valasaravakkam | Closed; trains skip |
| Alwarthirunagar | Closed; trains skip |
| Saligramam Warehouse | Closed; trains skip |
| Saligramam | Closed; trains skip |
Four of the six are on the double-decker section that carries Corridors 4 and 5 of the 118.9 km Phase 2 one above the other.

Why ATO mode decides the opening date
- Civil work: Entry structures and facades are being built, with completion expected by January or February 2027.
- Safety clearance: The Commissioner of Metro Railway Safety (CMRS) will inspect the stations, but “will not accept trains being operated in manual mode,” an official said.
- ATO first: Trains must run at least in Automatic Train Operation (ATO) mode, with an operator on board, before the stations can open.
- UTO later: “We expect to operate in UTO mode only by June or July 2027,” another official said, referring to unattended train operation.
Civil work slowed after trains began running, especially on the double-decker section, officials said.
Get the Daily Metro & Rail Brief
Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Why it matters
Arcot Road is one of west Chennai’s busiest corridors, and residents there now have to travel to Vadapalani or Porur to board. “If the station in my area opens, it would take barely five minutes to reach it, instead of the 20 minutes I now spend travelling to Vadapalani during peak hours,” said M Shankaran, a Saligramam resident. Follow Corridor 4 on our Chennai Metro Line 4 project page.