Mumbai Metro Line 3 Loaded Trials to Begin as Project Reaches 96% Completion

Date:

Share post:

MUMBAI (Metro Rail News): The Mumbai Metro Line 3 is nearing completion of its development phase, with loaded trials on Phase 1 from Aarey to Bandra Kurla Complex commencing this week. This stage involves testing the train’s performance under conditions that simulate full passenger loads, ensuring safety and operational efficiency before its public debut.

The concept of ‘loaded trials’ means filling the train coaches with stone-filled gunny bags to approximate the weight of a fully occupied train. Under realistic conditions, this process is essential for assessing the train’s dynamics, such as speed, suspension, and energy consumption. 

The trials will monitor aspects like coach oscillation on different track sections, including straight paths and curves, to ensure a smooth and safe ride for future passengers.

Enhanced Train Technology in Mumbai Metro

This Mumbai Metro features an advanced eight-car train setup with a 75% motor capacity, a notable increase from the 50% seen in previous lines. This enhancement aims to improve the train’s operational capabilities, particularly acceleration and handling. The Research, Design and Safety Organisation (RDSO) and the Commissioner of Metro Railway Safety (CMRS) will carry out the project’s inspection process shortly after the completion of loaded trials.

Current Project Status

Currently, the Metro 3 project is 96% complete, with the remaining work focusing on aesthetic and functional enhancements at stations. The Mumbai Metro Rail Corporation Limited (MMRCL) boasts a fleet of 19 rakes, ample to handle the operational demands of this phase. Once operational, the line expects to serve approximately 17 lakh passengers daily across 260 services.

Aqua Line
Aqua Line

Connectivity and Integration Efforts

Officials highlight ongoing efforts to ensure that Metro 3 is not just a standalone project but part of a larger, integrated transport network. These efforts include the development of multimodal connections at stations, enhanced pedestrian facilities, and clear signage to guide commuters. 

The line’s connectivity is further bolstered by the completion of the Aarey Depot link, which is essential for efficient train management and movement during the trials.

Future Developments and Impact

The focus is also on Phase 2, extending from BKC to Acharya Atre Chowk in Worli, which is already in an advanced completion stage. Moreover, preparations are underway to enable automatic train operations (ATO), which could potentially allow unmanned train operations, reflecting significant technological advancements in urban metro systems.


Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Bangalore Metro Yellow Line To Start Operations In January 2025 

Bangalore (Metro Rail News): Bangalore Metro Rail Corporation Limited( BMRCL) announced on 5 October that the commencement of...

2 Firms Qualify For DDC-03 Contract Of Pune Metro’s Aqua Line Extension 

Pune (Metro Rail News): Two Firms, SYSTRA MVA Consulting (India) and STUP – RITES JV have qualified for...

Titagarh Reveals Train Design For Ahmedabad Metro Phase 2

Ahmedabad (Metro Rail News): Following the inauguration, Ahmedabad Metro Phase 2 reached another milestone as the Titagarh Rail...

CLC Bridge Installed for Mumbai- Ahmedabad Bullet Train Project 

Surat ( Metro Rail News): This week, MG Contractors Pvt. Ltd. (MGCPL) achieved a milestone in the Mumbai...