DMRC Invites Bids for Package D2-C02 of Golden Line 

0
719
Delhi Metro Phase 4

Delhi (Metro Rail News): Delhi Metro Phase 4 advanced as Delhi Metro Rail Corporation (DMRC) invited bids for the Package D2-C02 of the Golden Line spanning 23.622 km from Aerocity to Tuglakabad through 15 stations. 

Package D2-C02’s Tender Details

Estimated CostRs. 456.06 crore
Deadline:36 months (3 years)
Pre-bid Meeting14 January 2025, at 11 am
Bid Submission Deadline:18 February 2025, at 3 pm
Technical Bid Opening19 February 2025, at 3 pm

Package D2-C02: Scope of Work 

The scope of work under Package D2-C02 includes the construction of a 7.298 km viaduct and the construction of only platform level of 7 stations and a Pre-Engineered Building Structure at all stations of the Lajpat Nagar to Saket G Block Corridor of Delhi Metro Phase 4 Project. 

Stations : 

  • Pushp Vihar
  • Saket District Court
  • Pushpa Bhawan
  •  Chirag Delhi 
  • GK-1
  • Andrews Ganj 
  • Lajpat Nagar

Note: All the stations mentioned above will have a length of 74 m except for the Pushp Vihar station (140 m) suggesting that stations will allow for 3 coaches train operations. 

Funding: The construction of the Package of D2-C02 will be financed through equity contributions from the government of India and the government of Delhi, along with other funding mechanisms employed by DMRC.

Further Information 

The construction of Line 11 connecting Saket G-Block and Lajpat Nagar will be carried through 2 packages. Package D2-C02 involves the construction of a viaduct and platform level of 7 stations on this corridor. However, the concourse level of these stations will be built under a separate package.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.