Delhi-Meerut RRTS Received ₹765 Cr, Nearly 98% of Delhi’s Pollution Charge Spending; ₹1,153 Cr Unspent, RTI Shows

3 min read
0
3
Delhi-Meerut RRTS Received ₹765 Cr, Nearly 98% of Delhi’s Pollution Charge Spending; ₹1,153 Cr Unspent, RTI Shows
Sarai Kale Khan station, the Delhi terminal of the Delhi-Meerut RRTS. Photo: Ravi Dwivedi / Wikimedia Commons (CC BY-SA 4.0)
Listen to this story
0:00

NEW DELHI (Metro Rail News): The Delhi-Meerut RRTS has received ₹765 crore from the Environment Compensation Charge (ECC) that Delhi levies on commercial vehicles entering the city, about 97.9% of everything the Delhi government has spent from the fund, according to replies under the Right to Information (RTI) Act reported by The Pioneer.

The same replies show that ₹1,153.93 crore of the money received by the Delhi government was still unspent as on 7 August 2026.

Delhi-Meerut RRTS and the pollution charge: the numbers

ItemAmount
ECC collected by MCD (6 November 2015 to 10 April 2026)₹2,247.66 crore
Received by the Delhi Transport Department₹1,935.44 crore
Spent₹781.51 crore
Unspent balance (as on 7 August 2026)₹1,153.93 crore
Gap between MCD collection and amount received₹312.22 crore (not reconciled in the replies)

The Municipal Corporation of Delhi (MCD) collects the charge through its toll contractor under Supreme Court orders and deposits it with the Delhi government’s Transport Department. The MCD’s Toll Tax Department gave the collection figure in an RTI reply dated 21 April, while the Transport Department supplied the expenditure statement.

Delhi-Meerut RRTS Namo Bharat standard coach interior
Inside a standard coach of a Namo Bharat train. Photo: Ravi Dwivedi / Wikimedia Commons (CC BY-SA 4.0)

Where the money went

PurposeAmount
National Capital Region Transport Corporation (NCRTC), Delhi-Meerut RRTS, sanctioned 12 March 2019₹265 crore
NCRTC, Delhi-Meerut RRTS, sanctioned 3 May 2023₹500 crore
Indian Oil Corporation, hydrogen-enriched CNG (HCNG) project₹15 crore (₹6 crore + ₹9 crore)
RFID toll system, pre-tendering costs₹93 lakh
Civil defence volunteers as traffic marshals, SPM Marg₹43 lakh
Non-motorised vehicle lanes on SPM Marg₹15 lakh

Together, the two payments to NCRTC account for ₹765 crore of the ₹781.51 crore spent.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Why the Delhi-Meerut RRTS drew on this fund

The ECC was imposed by the Supreme Court in 2015 to curb pollution from trucks entering Delhi, and RRTS funding has been part of the court’s hearings in the MC Mehta air-pollution case. In 2023, when the Delhi government said it could not fund its share of the Delhi-Alwar and Delhi-Panipat corridors, the court was not inclined to let it use ECC money for them, and asked for details of its advertising spending instead.

Shatabdi Nagar station on the Delhi-Meerut RRTS
Shatabdi Nagar station on the Meerut end of the corridor. Photo: Anshumalii / Wikimedia Commons (CC BY-SA 4.0)

Higher pollution charge from April 2026

After the Supreme Court approved the Commission for Air Quality Management’s recommendations on 12 March 2026, the Delhi government raised the charge from 1 April 2026. It rose from ₹1,400 to ₹2,000 for light-duty vehicles and two-axle trucks, and from ₹2,600 to ₹4,000 for three-axle and heavier trucks. The rates will increase by 5% every year.

Why it matters

The Delhi-Meerut RRTS is the only big project the fund has paid for, which makes it the main public-transport return on a decade of pollution charges. With more than ₹1,100 crore still unspent and the rates now higher, the fund could again become a source for Delhi’s share of the next Namo Bharat corridors. Follow the corridor on our Delhi-Meerut RRTS project page.

Also Read: Namo Bharat Crosses 5 Crore Passenger Journeys, Latest Crore Added in Just 93 Days

namo bharat train delhi karnalRead nextNCRTC Awards ₹60.23 Cr Contract to Shift HVPNL Transmission Lines on Delhi-Panipat-Karnal Namo Bharat Corridor11 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here