Home High Speed Rail Projects Bullet Train Project Achieves 2nd Mountain Tunnel Breakthrough in Maharashtra 

Bullet Train Project Achieves 2nd Mountain Tunnel Breakthrough in Maharashtra 

0
37
Mountain Tunnel Breakthrough for Bullet Train Project

The Mumbai-Ahmedabad Bullet Train Project achieved a major milestone with the successful breakthrough of the second mountain tunnel in Palghar, Maharashtra on 3 Feb 2026. This tunnel is 454 metres long with a width of 14.4 metres, and will accommodate both up and down tracks for the Mumbai-Ahmedabad Bullet Train project.

image 1

The mountain tunnel (MT-6) was excavated from both ends using New Austrian Tunnelling Method (NATM), a cutting-edge drill-and-controlled blast method. The excavation is completed within 12 months. 

InnoMetro_2026_

As per the Release,Union Minister Ashwini Vaishnaw congratulated the entire high-speed rail team for their remarkable progress. He said the pace at which the team is working has instilled new confidence in the country. The project is drawing global attention and appreciation due to several new innovations in construction and technology. He highlighted that many advanced construction technologies and large machines being used for the project are manufactured in India.

image 2

In Maharashtra, construction work is advancing rapidly across multiple sites. Currently,  seven mountain tunnels are currently underway in Palghar district. The current status of the tunnel have been mentioned below:

Sr. No Mountain Tunnel No.Length % Completion Remarks 
1MT-10.82016% 
2MT-20.228 Preparatory works underway
3MT-31.40341% 
4MT-41.26032% 
5MT-51.48057%Breakthrough achieved on 02 Jan 2026
6MT-60.45447%Breakthrough achieved today
7MT-70.41729% 

The Mumbai-Ahmedabad High Speed Rail Project is an under construction high speed rail project. The project spans 508 kilometres between Mumbai and Ahmedabad covering 12 stations. 

Stations: Mumbai (Bandra Kurla Complex), Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad, and Sabarmati

As on 27 Jan 2026, around 334 km of viaducts, 17 river bridges, and 12 major crossings over national highways, railways, and other infrastructure have been completed. Track laying and electrification works have picked up pace in the Gujarat section of the project for the Mumbai-Ahmedabad Bullet Train Project. 


Explore how AI-integrated systems are improving comfort, connectivity, and accessibility for passengers across metro and rail networks at the 6th edition of InnoMetro, India’s leading expo for the Metro & Railway industry which is going to held on 21-22 May 2026 at Bharat Mandapam, New Delhi

Register now: https://innometro.com/visitor-registration/

NO COMMENTS

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.