Mumbai-Ahmedabad Bullet Train Project: Slab casting started for the Virar Station

Mumbai-Ahmedabad Bullet Train Project: Slab casting started for the Virar Station
Listen to this story
0:00

The Mumbai-Ahmedabad Bullet Train Project progressed as the Casting of the first slab started at the Virar Bullet Train station. There will be 9 such slabs at this level, which will form the base for track laying works at the station. 

Screenshot 2025 06 04 121536

The Virar Bullet Train station will have two levels with a total length of 425 meters.

  • Concourse level 
  • Rail level  

The first slab cast at the Virar Bullet Train station is 50 meters in length and 35.32 meters in width. The slab has a thickness of approximately. 300 mm, utilising 1555 cubic meters of concrete.

Recent Train Trials for Mumbai-Ahmedabad Bullet Train Project 

Recently, the first Shinkansen bullet train of the Mumbai-Ahmedabad Bullet Train Project entered the trial phase in Japan. As part of the Indo-Japanese collaboration, Japan will provide two Shinkansen train sets—one from the E5 series and one from the E3 series—for initial inspection and performance testing. 

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

About the Mumbai-Ahmedabad Bullet Train Project 

The Mumbai Ahmedabad Bullet Train Project is an under-construction high-speed rail line that spans 508 km between Mumbai and Ahmedabad through 12 stations. 

Out of 12 stations planned for MAHSR, 4 stations are located in Maharashtra, while the remaining  8 stations are located in Gujarat. 

Project Overview

High-Speed Rail in India – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →
Untitled design 48Read nextBengaluru Metro Pink Line: PM Modi to Inaugurate Agrahara-Tavarekere Stretch on November 13, Network to Reach 103.6 km4 Nov 2026

Add Metro Rail News as a preferred source on Google

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here