Kanpur Metro Update: TBM Azad Starts Tunneling

Kanpur Metro Update: TBM Azad Starts Tunneling
TBM Azad Starts Tunneling PC: Atul SIngh Yadav

KANPUR (Metro Rail News): Afcons commissioned its first Tunnel Boring Machine – TBM Azad (S-640B), for constructing Kanpur Metro’s underground package KNPCC-06. 

This is Kanpur metro’s Third TBM to be deployed so far for constructing 23.785 Km line 1 between IIT Kanpur & Naubasta. Afcons had started lowering the tunnel into the Kanpur Central shaft in August 2023. 

Package KPNCC-06 connects Nayaganj Station & Transport Nagar ramp with three stations in between namely Kanpur Central, Jhakarkatti, and Transport Nagar, at an estimated cost of Rs 1087.67 Crores. The contract was awarded to Afcons-SAM JV in March 2022 with a deadline of 36 months. 

This is the very same machine that had constructed the Kolkata Metro’s 16.34 Km line-2 passing under the Hoogly River. 


Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.

Project Overview

Kanpur Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here