AGRA (Metro Rail News): Agra Metro Phase 1 Project progressed as Larsen & Toubro (L&T) launched the first set of 2 U-girders for the construction of the Line 2, which spans 15.09 km connecting Agra Cantonment – Kalindi Vihar through 14 elevated stations.

1751342496683
Image Credit: Hirak Senapati

This development was recorded under package AGCC-07. The launching of the U girder took place between piers P/18 and P19 in Agra Cantonment. Each girder spans  27.90m and weighs 155MT.

In November 2024, L&T bagged Package AGCC-07 from Uttar Pradesh Metro Rail Corporation (UPMRC) at Rs. 1242.79 crore and 24 24-month deadline. 

1751342467474
Image Credit:Hirak Senapati

As per the construction plan, L&T will cast 761 piers for the construction of Line 2’s superstructure and will launch 930 U-girders to form its viaduct. 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

The scope of work under Package AGCC-07 includes the construction of Line 2’s viaduct along with 14 elevated stations. The contract also includes the 530m viaduct to Line-2’s Kalindi Vihar Depot and a 2.61 km viaduct from north of Sadar Bazar metro station to Line-1’s PAC Depot.

UPMRC’s Brief Scope: Design and Construction of Main Line Elevated Viaduct from Agra Cantt. Metro Station to Kalindi Vihar Metro Station [Chainage (-77m) to 15016m] including Viaduct Connection with Ramp (Chainage 0.00m to 2610m) from (nearby) Sadar Bazar Metro Station to existing Corridor-1 Depot at PAC ground & Corridor-2 Depot Entry/Exit lines Viaduct with Ramp (Chainage 0.00m to 530m) and 14 nos. of Elevated Stations i.e., Agra Cantt, Sadar Bazar, Pratap Pura, Collectorate, Agra College, Hariparvat Chauraha, Sanjay Place, M.G. Road, Sultanganj crossing, Kamla Nagar, Ram Bagh, Foundary Nagar, Agra Mandi & Kalindi Vihar metro stations including Civil, Associated Ancillary Structures, Architectural Finishes, Water Supply, Sanitary Installation, Drainage, External Development, Fire Fighting, Fire Detection, E&M works and PEB structures in Corridor-2 of Agra Metro at Agra, Uttar Pradesh, India

Guide

Agra Metro: the complete guide

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here