Maha Metro May Execute Ramwadi-Wagholi Double-Decker Corridor as Single Agency

0
2
Maha Metro May Execute Ramwadi-Wagholi Double-Decker Corridor as Single Agency
Maha-Metro may build the Ramwadi-Wagholi double-decker corridor as a single agency, with MSIDC reimbursing the road-flyover cost.
Listen to this story
0:00

PUNE (Metro Rail News): Maharashtra Metro Rail Corporation Limited (Maha Metro) is likely to execute the proposed double-decker structure on Pune Metro’s Ramwadi-Wagholi corridor as a single agency to avoid coordination issues between two major infrastructure projects. Under the proposed arrangement, Maha Metro would build the integrated structure, while the Maharashtra State Infrastructure Development Corporation (MSIDC) would reimburse the cost of the road-flyover component.

The proposal aims to bring the metro extension and the Pune-Shirur elevated corridor under one executing agency. It will also reduce the risk of duplicated work and construction-related delays. The final execution model, however, is yet to be approved.

Integrated metro and road flyover planned

The proposed double-decker structure will extend from Ramwadi towards Kharadi Chowk and Vitthalwadi in Wagholi. It will carry the metro corridor on the upper deck and the road flyover below. The structure is intended to integrate two projects:

  • Ramwadi-Wagholi Metro Extension: Maha Metro is developing the metro corridor to extend connectivity towards Wagholi.
  • Pune-Shirur Elevated Corridor: MSIDC is handling the proposed road corridor, for which it has already floated a tender.

The two projects overlap along parts of the proposed route. Their alignment and intersection points are being examined by the agencies to ensure that both infrastructure components can be accommodated within a common structure.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Maha Metro may handle construction and MSIDC may fund road component

The proposed arrangement would make Maha Metro responsible for executing the entire double-decker structure, including both the metro and road-flyover levels. MSIDC would bear its share of the expenditure for the road component by reimbursing Maha Metro. An official familiar with the discussions said a single-agency approach would help avoid the complications of having separate agencies construct the two levels independently.

Atul Gadgil, Director (Works) at Maha Metro, said discussions were underway to settle the execution arrangement and the applicable construction rates. However, MSIDC Managing Director Brijesh Dixit said the model had not yet been finalized. He added that the agencies could either appoint one agency to construct the integrated structure or execute the two levels separately.

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi

Three agencies involved in project coordination

The proposed infrastructure involves three agencies:

  • Maha Metro: Responsible for the Ramwadi-Wagholi metro extension and a possible single-agency role in constructing the integrated structure.
  • MSIDC: Developing the Pune-Shirur elevated corridor and expected to fund the road-flyover component.
  • Pune Municipal Corporation (PMC): Involved in coordination for the proposed infrastructure.

MSIDC has begun preparatory activities for the Pune-Shirur corridor, including land acquisition and shifting of utilities. These activities will be important for determining the construction sequence and coordinating the road and metro alignments.

Execution model yet to be finalised

Although the single-agency approach is being considered, the three agencies have not reached a final decision. The construction arrangement and cost-sharing mechanism will need to be settled before work on the integrated structure can proceed under the proposed model. No construction start date or completion timeline has been announced for the double-decker stretch.

Also Read: Differences Between PMC and Maha Metro: Pune Metro Tender Delayed

Pune MetroRead nextDifferences Between PMC and Maha Metro: Pune Metro Tender Delayed6 Nov 2026

Add Metro Rail News as a preferred source on Google

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here