Bangalore (Metro Rail News): Bangalore Metro progressed as SYSTRA MVA Consulting has been awarded 3 major Detailed Design Consultant (DDC) contracts for Bangalore Metro Phase 3 project.
Bidding Process
Bangalore Metro Rail Corporation Ltd. (BMRCL) floated tenders for 3 DDC contracts of Bangalore Metro Phase 3 in October with a 1460 day (4 year) contract duration.
On 23 December 2024, technical bids were opened revealing that 6 firms have submitted bids for each contract. So BMRCL received 18 bids in total.
On 29 January 2025, financial bids were opened revealing that SYSTRA has become the lowest bidder for all 3 DDC contracts.
DDC- 1
Financial Bid Values
Bidder Name | Bid Value (₹) | Rank |
Systra MVA Consulting | 9.9 Cr | L1 |
L&T Infrastructure Engineering Limited | 10.7 Cr | L2 |
Meinhardt (Singapore) Pte. Ltd. | 13.2 Cr | L3 |
AECOM Singapore Pte. Limited | 15.8 Cr | L4 |
SMEC International Pty. Ltd. | 15.9 Cr | L5 |
Shirish Patel and Associates Consultants Pvt. Ltd. | 24.4 Cr | L6 |
DDC-1’s Brief Scope: Detailed Design Consultancy Services for all Structures including Elevated Viaduct, Double Decker, Single Decker/Double Decker Stations, Entry/Exit Structures, Loops and Ramps for Road Flyovers, Subways, FOBs, Multi-Modal Integration Structure, etc. from JP Nagar 4th Phase Station (Excl) to BDA Complex Nagarbhavi Station (Incl) (from Chainage -0.330 to 16.791) of Corridor-1 for Bangalore Metro Rail Project, Phase-3.
DDC- 2
Financial Bid Values
Bidder Name | Bid Value (₹) | Bid Rank |
Systra MVA Consulting | 7.9 Cr | L1 |
L and T Infrastructure Engineering Limited | 8.7 Cr | L2 |
SMEC International Pty. Ltd. | 11.5 Cr | L3 |
Meinhardt (Singapore) Pte. Ltd. | 11.6 Cr | L4 |
Aecom Singapore Pte. Limited | 14.9 Cr | L5 |
Shirish Patel and Associates Consultants Pvt Ltd | 16.6 Cr | L6 |
DDC-2’s Brief Scope: Detailed Design Consultancy Services for all Structures including Elevated Viaduct, Double Decker, Single Decker/Double Decker Stations, Entry/Exit Structures, Loops and Ramps for Road Flyovers, Subways, FOBs, Multi Modal Integration Structure and Depots etc. from Sumanahalli Cross Station (excl) to Kempapura Station (excl) (from Chainage: 17.473 To 30.321) of Corridor-1 for Bangalore Metro Rail Project, Phase-3
DDC-3
Financial Bid Value
Bidder Name | Bid Value (₹) | Bid Rank |
Systra | 10.7 Cr | L1 |
Meinhardt (Singapore) Pte. Ltd. | 12.6 Cr | L2 |
SMEC International Pty. Ltd. | 14.5 Cr | L3 |
L and T Infrastructure Engineering Limited | 17.7 Cr | L4 |
Shirish Patel and Associates Consultants Pvt Ltd | 20.5 Cr | L5 |
AECOM Singapore Pte. Limited | 20.8 Cr | L6 |
DDC-3’s Brief Scope: Detailed Design Consultancy Services for all Structures including Elevated Viaduct, Double Decker, Single Decker/Double Decker Stations, Entry/Exit Structures, Loops and Ramps for Road Flyovers, Subways, FOBs, Multi Modal Integration Structure and Depots etc. from Hosahalli Station (Incl) to Kadabagere Station (Incl) with Lap Portion and Sumanahalli Cross Station, Depots at Sumanahalli and Peenya (from Chainage: -0.450 to 12.050) of Corridor-2 for Bangalore Metro Rail Project, Phase-3
About Bangalore Metro Phase 3
The routes in Bangalore Metro Phase 3 will traverse through Western Bangalore covering a total distance of 44.65 km via 2 new corridors.
Corridor Name | Route Description | Length | Total no. of Stations |
Corridor 1 (Orange Line) | Kempapura – JP Nagar 4th Phase via Outer Ring Road (ORR) | 32.15 km | 22 |
Corridor 2 | Kadabagare – Hosahalli via 9 stations | 12.5 km | 9 |