Bangalore Metro: 2 Firms Receives LoA for Architectural Finishing Contracts for Phase 2’s Reach 6

2 min read
0
741
Bangalore Metro: 2 Firms Receives LoA for Architectural Finishing Contracts for Phase 2’s Reach 6
PM Modi is set to inaugurate Bengaluru Metro's 7.5 km Pink Line elevated section on November 13, taking the network to 103.6 km.
Listen to this story
0:00

Bangalore (Metro Rail News): Anu Constructions and DC Facility Management Services have received Letters of Acceptance (LoAs) for the two balancing architectural finishing contracts of Bangalore Metro Phase 2’s Reach 6. 

Contract Bagged By Anu Constructions 

Artboard 1 1@4x
  • Anu Construction Bid Value: ₹ 27 Cr 
  • Contract Duration: 395 Days

Scope of Work 

Anu Construction will be responsible for Balance Architectural Finishing Works for Six Underground Metro Stations of RT-03 and RT-04 and one Elevated Metro Station in the Reach-6 line of the Bangalore Metro Rail Project, Phase-2 under Package-2.

Stations 

  • Kalena Agrahara ( Elevated) 
  • Cantonment
  • Pottery 
  • Tannery Road
  • Venkateshpura
  • KG Halli
  • Nagawara

BMRCL Brief Scope of Work: Balance Architectural Finishing Works for Six Underground Metro Stations (Cantonment, Pottery, Tannery Road, Venkateshpura, KG Halli and Nagawara) of RT-03 and RT-04 and one Elevated Metro Station (Kalena Agrahara) in Reach-6 line of Bangalore Metro Rail Project, Phase-2 under Package-2.

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

Contract Bagged By DC Facility Management Services

Artboard 1 2@4x 1
  • DC facility Management Services Bid Value: ₹ 23.7 Cr 
  • Contract Duration: 395 Days

Scope of Work 

DC facility management services will be responsible for the Balance Architectural Finishing Works for Six Underground Metro Stations of RT-01 and RT-02 in the Reach-6 line of the Bangalore Metro Rail Project, Phase-2, under Package-1

Stations 

  • Dairy Circle
  • Lakkasandra 
  • Langford 
  • Rashtriya Military School
  • MG Road 
  • Shivajinagar

BMRCL Brief Scope of Work: Balance Architectural Finishing Works for Six Underground Metro Stations of  RT-01 and RT-02 in Reach-6 line of Bangalore Metro Rail Project, Phase-2 under Package-1 

bengaluru metro pink line underground dairy circle stationRead nextBengaluru Metro Pink Line: BMRCL Seeks CMRS Nod to Start Underground Trials up to Shivajinagar21 Nov 2026

Add to Preferred Sources

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here