South Central Railway Floats ₹3,103.69 Cr Tender for Kharsia-Balodabazar New Double Line in Chhattisgarh

South Central Railway Floats ₹3,103.69 Cr Tender for Kharsia-Balodabazar New Double Line in Chhattisgarh
South Central Railway Floats ₹3,103.69 Cr Tender for Kharsia-Balodabazar New Double Line in Chhattisgarh

CHHATTISGARH (Metro Rail News): South Central Railway has invited bids for a ₹3,103.69 crore EPC contract to construct a new broad-gauge double railway line from Kharsia to Balodabazar in Chhattisgarh. The project will also include Y-connectivity from Jharadih and cover major civil, track, electrical and signalling works. 

Tender details 

Details Information
Tender NumberCAO-C-BSP-26-27-16 
Estimated Cost ₹3,103.69 crore
EMD₹62.08 crore
Pre-Bid Meeting01 September 2026, (11:00 AM) 
2d Pre-Bid Meeting22 September 2026, (11:00 AM) 
Bid Submission Deadline08 August 2026,  (22:56 PM) to 11 November 2026 (15:00 PM)  
Completion Period 1275 Days 

Scope of work

The contract includes construction of new BG Double Line from Kharsia (Km 0.00) to Balodabazar (Km 110.500) and Y-connectivity from Jharadih including earthwork in formation, bridges, ROR (Rail Over Rail), ROB (Road Over Bridge), RUB (Road Under Bridge), service buildings, staff quarters, P-Way works (including supply of Ballast, P-way material except Rail), Electrification (2×25 KV OHE, PSI, PLC & Electrical General work), and Signalling & Telecommunication works, along with allied and associated miscellaneous works in connection with Kharsia- Parmalkasa 5th & 6th New BG Line Project under South East Central Railway in the State of Chhattisgarh. 

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

About the project

The new line will run between Kharsia and Balodabazar in Chhattisgarh and will form part of the broader Kharsia-Parmalkasa 5th and 6th New Broad Gauge Line Project. The package brings together railway formation, structures, track, electrification and signalling works under a single EPC contract.