CHENNAI (Metro Rail News): A Shellinfo Singapore & Shellinfo India consortium has been awarded a contract for the Automatic Fare Collection System of 26.09 Km of Chennai Metro.
Bids Invited
CMRL had invited bids for the same in February 2023. The New Development Bank is financing it with an unknown estimate and a deadline of 4.3 years.
Bidders
The bidders for the contract are as follows:
Firm | Bid |
Shellinfo | 42.57 Crores |
Aurionpro Solutions | 46.13 Crores |
Nippon Signal | 94.87 Crores |
MSI Global | 96.63 Crores |
Scope of the Contract
The contract scope includes Design, Manufacture, Supply, Installation, Testing, Commissioning and integration of the Back Office for the Automatic Fare Collection (AFC) System for CMRL Phase II – Corridor 4.
Chennai Metro, Phase 2
Phase 2 of the Chennai Metro Project pitches for a 118.9 km Network consisting of 3 corridors, namely:
- Corridor 3: Madhavaram to SIPCOT (45.8 Km) – Work is underway on this line, with land acquisition in progress. It will be connecting major IT hubs and educational institutions.
- Corridor 4: Lighthouse to Poonamalle Bypass (26.1 Km)- This line faces delays due to Coastal Regulation Clearance issues. It will be improving connectivity to the northern suburbs of Chennai.
- Corridor 5: Madhavaram to Sholinganallur (47 Km)- Work is underway on this line, with 63 steel bridges already installed. It will be the first of lines in the Chennai metro rail network to feature driverless metros.
Currently, 36 out of the 61 packages, encompassing Civil, Track, and System components for Corridor 3, Corridor 4, and Corridor 5, have been granted, and construction is underway. The project is scheduled for completion by the conclusion of 2026.
Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.