Rail Connectivity to Sikkim gets fast tracked

Sivok Rangpo Rail project shows perceptible progress, 58% of mining work completed in 14 Main Tunnels- 22.23 km of 38.65 km, 42% work completed on 13 Major bridges.

0
962
Rail Connectivity to Sikkim gets fast tracked
Rail Connectivity to Sikkim gets fast tracked

SIKKIM (Metro Rail News): Ministry of Railways has been laying great emphasis on improvement in Railway infrastructure in the North-eastern region. North Eastern Region is served by Northeast Frontier Railway consisting of 8 states i.e. Assam, Arunachal Pradesh, Nagaland, Manipur, Mizoram, Tripura, Meghalaya and Sikkim.

 

Out of 8 States of North Eastern Region, rail network connectivity now exists in 7 States. For, Sikkim, the new line project Sivok-Rangpo (44 km) was sanctioned. The foundation stone of this project was done by the Minister of Railway, Govt. of India at Sivok (West Bengal) on 30.10.2009 & at Rangpo (in Sikkim) by Vice President of India on the same day.

Out of the Total length of 44.96 km, 38.65 km (86%) is in tunnels, 2.24 km (5%) in Bridges and4.79 km (9%) length in open cutting/filling of station yards. The proposed line consists of 14 tunnels with longest tunnel of 5.30 km& the smallest tunnel covering 538 metres. Five stations including Sivok and Rangpo are planned on proposed Railway Line. Four stations are proposed to be open crossing stations e.g., Sivok, Riyang, Melli & Rangpo and one underground halt station e.g. Teesta Bazar.

Tunnelling which is about 86% of the total length is constructed by the latest Technique called NATM (New Austrian Tunnelling Method). The work of this project is supervised by International Consultants so that Safety and Quality are ensured. IRCON is taking all the measures so that there is minimum disturbance to the Environment and Forest.