Delhi-Gurgaon-Rewari-Alwar: Information, Route Maps & Project Updates

AN OVERVIEW

Delhi-Gurgaon-Rewari-Alwar Regional Rapid Transit System (Delhi–Alwar RRTS) is a 164 km long proposed, semi-high speed rail corridor connecting Delhi, Gurgaon, Rewari and Alwar.

It is one of the three rapid-rail corridors planned under Phase-1 of the Rapid Rail Transport System of the National Capital Region Transport Corporation(NCRTC).

With a maximum speed of 160 kmph and average speed of 105km/h, the distance between Delhi and Alwar will be covered in 104 minutes.

Delhi – Alwar RRTS

Phase 1 – Delhi – Gurgaon – SNB
Total Distance – 106 km
Phase 2 – SNB – Behror – Sotanala
Total Distance – 35 km
Phase 3 – SNB to Alwar
Total Distance – 58 km

• Station Type – Elevated, Underground & At-Grade
• Depot – Dharuhera & Alwar
• Main-Line Stations: Sarai Kale Khan – Jor Bagh – Munirka – Aerocity – Udyog Vihar – Gurgaon Sector 17 – Rajiv Chowk – Kherki Daula – Manesar – Panchgaon – Bilaspur Chowk – Dharuhera Depot – MBIR – Rewari – Bawal – SNB – Khairthal – Alwar.
• Spur Line Stations: Shahjahanpur – Neemrana – Behror – Sotanala
• Estimated Project Cost – Rs 37,000 crores.

Some Key Highlights

• Design Speed – 180 kmph
• Running Speed – 160 kmph
• Track Gauge Standard Gauge – 1435 mm
• Rolling Stock – Aerodynamic, 3.2 m wide x 22 m long, stainless steel/aluminium body
• Signalling – European Train Control System Level 2 of ERTMS
• Traction – 1 x 25 KV AC overhead catenary
• Coach Classes – Economy and Business

Contractors of Delhi – Alwar 

  • A Joint Venture of URS Scott Wilson and CEG – Feasibility Study for connecting SNB Urban Complex to Sotanala RIICO Industrial Area
  • UMTC – Feasibility Study for Delhi – SNB Urban Complex division
  • PricewaterhouseCoopers – Financial Consultant
  • CEG Test House and Research Centre Pvt Ltd. – Geotechnical Investigation: from Sarai Kale Khan – IDPL Complex in Gurgaon
  • S S Solution – Final Location Survey, Topographic Survey & Other Misc Surveys
  • Shree Balaji Test House Pvt. Ltd. – Geotechnical Investigation for Underground Section: from Rajiv Chowk – Kherki Daula
  • CEG Test House and Research Centre Pvt. Ltd. – Geotechnical Investigation
  • Continental Piling & Excavation Pvt. Ltd. – Initial Pile Load Test
  • RITES – Geotechnical Investigation
  • L&T – Detailed Design Consultant (DDC)
  • GR Infra – Construction