Delhi Metro Magenta Line

Operational Operator: Delhi Metro Rail Corporation (DMRC) Length: 50.18 km Since: 25/12/2017 Updated: Official site ↗

As of 17 Oct 2026, Delhi Metro Magenta Line is operational (since 25 Dec 2017). Latest news: 29 Sep 2026.

The Delhi Metro Magenta Line (Line 8) runs from Botanical Garden to Krishna Park Extension, and separately from Deepali Chowk to Majlis Park: about 50 km and 33 stations as of October 2026. The Krishna Park Extension section opened in January 2025 and Deepali Chowk to Majlis Park in March 2026. DMRC targets end-2026 for the gap via Peeragarhi. Fares are ₹11 to ₹64.

Why it matters

The Magenta Line was India's first driverless metro line and links Noida with south Delhi and IGI Airport Terminal 1 without passing through central Delhi. Its Phase 4 extension turns it into a north-south arc through west and north Delhi, adding interchanges at Peeragarhi, Madhuban Chowk, Haiderpur Badli Mor, Majlis Park, Azadpur and Pulbangash. Once it reaches RK Ashram Marg and then Indraprastha through the Central Vista, it will connect outer residential areas directly with the government district.

Key facts

  • Operator: Delhi Metro Rail Corporation (DMRC)
  • Length in service: 50.18 km, 33 stations open and 14 under construction
  • Status (October 2026): Partially operational, run as two separate stretches as of October 2026: Botanical Garden to Krishna Park Extension (26 stations) and Deepali Chowk to Majlis Park (7 stations, opened 8 March 2026), about 50 km and 33 stations in all. The Phase 4 gap from Krishna Park Extension to Deepali Chowk (6 new stations, including the Peeragarhi interchange with the Green Line) is targeted by DMRC for the end of 2026. Majlis Park to RK Ashram Marg (8 stations, partly underground) is under construction, and the Phase 5A RK Ashram Marg to Indraprastha extension has started.
  • Cost: Janakpuri West to RK Ashram Marg extension is part of the ₹24,948.65 crore Phase 4 priority corridors package (three corridors, approved March 2019); no separate line figure officially published
  • Trains: Hyundai Rotem 6-coach driverless trains on the Phase 3 line; Alstom Metropolis trainsets for the Phase 4 extension; standard gauge (1,435 mm), 25 kV AC overhead, maximum speed 100 km/h

Delhi Metro Magenta Line stations

The 47 stations below run from Botanical Garden to RK Ashram Marg. Interchanges are listed where a station connects with another line or a railway station.

#StationConnects to
1Botanical GardenLine 3 (Blue)
2Okhla Bird Sanctuary
3Kalindi KunjGolden Line extension (Phase 5A, approved)
4Jasola Vihar Shaheen Bagh
5Okhla Vihar
6Jamia Millia Islamia
7Sukhdev Vihar
8Okhla NSIC
9Kalkaji MandirLine 6 (Violet)
10Nehru Enclave
11Greater Kailash
12Chirag DelhiGolden Line branch, Lajpat Nagar to Saket G Block (under construction)
13Panchsheel Park
14Hauz KhasLine 2 (Yellow)
15IIT
16R K Puram
17Munirka
18Vasant Vihar
19Shankar Vihar
20Terminal 1 IGI AirportIGI Airport Terminal 1 / Golden Line extension (Phase 5A, approved)
21Sadar Bazar Cantonment
22Palam
23Dashrathpuri
24Dabri Mor Janakpuri South
25Janakpuri WestLine 3 (Blue)
26Krishna Park Extension
27Keshopur (under construction)
28Paschim Vihar (under construction)
29Peeragarhi (under construction)Line 5 (Green)
30Mangolpuri (under construction)
31Mangolpur Kalan West Enclave (under construction)
32Pushpanjali (under construction)
33Deepali Chowk
34Madhuban ChowkLine 1 (Red)
35Uttari Pitampura Prashant Vihar
36Haiderpur Village
37Haiderpur Badli MorLine 2 (Yellow)
38Bhalaswa
39Majlis ParkLine 7 (Pink)
40Azadpur (under construction)Line 2 (Yellow) / Line 7 (Pink)
41Ashok Vihar (under construction)
42Nanak Piao Derawal Nagar (under construction)
43Ghanta Ghar (under construction)
44Pulbangash (under construction)Line 1 (Red)
45Sadar Bazar (under construction)
46Nabi Karim (under construction)
47RK Ashram Marg (under construction)Line 3 (Blue) / Central Vista corridor to Indraprastha (Phase 5A)

Sections and opening dates

SectionStationskmStatusOpened or expected
Botanical Garden to Kalkaji Mandir912.64Operational (Phase 3)2017-12-25
Kalkaji Mandir to Janakpuri West1624.82Operational (Phase 3)2018-05-28
Janakpuri West to Krishna Park Extension12.8Operational (Phase 4, first Phase 4 section to open)2025-01-05
Krishna Park Extension to Deepali Chowk6Under construction (Phase 4); Peeragarhi station civil work about 90% done (DMRC, October 2026)expected end of 2026 (DMRC official, reported October 2026)
Deepali Chowk to Majlis Park79.92Operational (Phase 4)2026-03-08
Majlis Park to RK Ashram Marg8Under construction (Phase 4); tunnelling under the Red Line at Pulbangash done on the down line by December 2025no official date announced
RK Ashram Marg to Indraprastha99.913Approved under Phase 5A (Central Vista corridor, fully underground); foundation stone laid, tenders and early works under wayno official date announced

Explore more

Official source: www.delhimetrorail.com

Latest updates

59 tenders tracked →

See all news & updates →

Phases

PhaseLinesStationsLength (km)Status
Botanical Garden to Kalkaji MandirBotanical Garden to Kalkaji Mandir912.64Operational (Phase 3)
Kalkaji Mandir to Janakpuri WestKalkaji Mandir to Janakpuri West1624.82Operational (Phase 3)
Janakpuri West to Krishna Park ExtensionJanakpuri West to Krishna Park Extension12.8Operational (Phase 4, first Phase 4 section to open)
Krishna Park Extension to Deepali ChowkKrishna Park Extension to Deepali Chowk6Under construction (Phase 4); Peeragarhi station civil work about 90% done (DMRC, October 2026)
Deepali Chowk to Majlis ParkDeepali Chowk to Majlis Park79.92Operational (Phase 4)
Majlis Park to RK Ashram MargMajlis Park to RK Ashram Marg8Under construction (Phase 4); tunnelling under the Red Line at Pulbangash done on the down line by December 2025
RK Ashram Marg to IndraprasthaRK Ashram Marg to Indraprastha99.913Approved under Phase 5A (Central Vista corridor, fully underground); foundation stone laid, tenders and early works under way

Milestones

  • Botanical Garden to Kalkaji Mandir section opens, inaugurated by PM Narendra Modi
  • Kalkaji Mandir to Janakpuri West section opens, completing the 37.46 km Phase 3 line
  • Union Cabinet approves three Phase 4 priority corridors, including the 28.92 km Janakpuri West to RK Ashram Marg extension of the Magenta Line
  • Driverless train operations begin on the Magenta Line, a first for an Indian metro
  • Tunnelling between Krishna Park Extension and Keshopur completed
  • CMRS inspects the Janakpuri West to Krishna Park Extension section
  • 2.8 km Janakpuri West to Krishna Park Extension section opened by PM Narendra Modi, the first Phase 4 section in service
  • DMRC finishes the down-line tunnel between Pulbangash and Sadar Bazar beneath the operating Red Line
  • Union Cabinet approves Phase 5A, including the 9.913 km RK Ashram Marg to Indraprastha (Central Vista) extension
  • 9.92 km Deepali Chowk to Majlis Park section with 7 stations opened by PM Narendra Modi, along with the foundation stone for Phase 5A
  • DMRC tenders a passenger link between the Pink Line and the elevated Line 8 station at Azadpur
  • DMRC says Peeragarhi interchange station is about 90% complete and the Krishna Park Extension to Deepali Chowk stretch is expected to open by the end of 2026

Fares

Delhi Metro Magenta Line fares range from ₹11 (DMRC network fare, revised 25 August 2025) to 10%, plus 10% more in off-peak hours, set by Delhi Metro Rail Corporation (DMRC).

Distance / zoneFare
Minimum fare₹11 (DMRC network fare, revised 25 August 2025)
Maximum fare₹64 (journeys over 32 km)
Smart card discount10%, plus 10% more in off-peak hours

Frequently asked questions

What is the route of the Delhi Metro Magenta Line?

It runs from Botanical Garden in Noida via Kalkaji Mandir, Hauz Khas and Terminal 1 IGI Airport to Janakpuri West and Krishna Park Extension. A second stretch runs from Deepali Chowk to Majlis Park; the two will join when the Krishna Park Extension to Deepali Chowk section opens.

When did the Krishna Park Extension and Deepali Chowk to Majlis Park sections open?

The 2.8 km Janakpuri West to Krishna Park Extension section opened on 5 January 2025. The 9.92 km, 7-station Deepali Chowk to Majlis Park section opened on 8 March 2026.

When will Krishna Park Extension to Deepali Chowk open?

A DMRC official said in October 2026 that the section, including the Peeragarhi interchange with the Green Line, is expected to open by the end of 2026. No CMRS inspection has been reported yet.

Is the Magenta Line driverless?

Yes. Driverless operations began on 28 December 2020, the first in India.

Will the Magenta Line go to RK Ashram Marg and Indraprastha?

Yes. Majlis Park to RK Ashram Marg is under construction under Phase 4, and the 9.913 km underground RK Ashram Marg to Indraprastha extension via Central Secretariat and India Gate was approved under Phase 5A, with its foundation stone laid in March 2026.

Which stations are interchanges on the Magenta Line?

Botanical Garden and Janakpuri West (Blue Line), Kalkaji Mandir (Violet), Hauz Khas and Haiderpur Badli Mor (Yellow), Madhuban Chowk (Red) and Majlis Park (Pink). Terminal 1 IGI Airport serves the domestic terminal.

What is the fare on the Magenta Line?

Delhi Metro's distance-based fares apply, from ₹11 to ₹64 since 25 August 2025, with a 10% smart card discount.

Journey Planner & Route Map

Awarded tenders & contracts

No awarded tenders or contracts recorded yet.

Ongoing tenders

TenderAgencyValueBid dueStatus
Electrical work consultancy tender floated for Delhi Metro & Jaipur MetroDMRCSubscribersOpen
Delhi Metro Phase-V(A): DMRC Floats ₹21.50 Cr Tender for Central Vista Corridor’s Twin Tunnels and StationsDMRCOpen
Delhi Metro Phase-4: DMRC Floats Signalling Tender for Lajpat Nagar-Saket G Block CorridorDMRCSubscribersSubscribersClosing Soon
Delhi Metro: DMRC invites bids for civil maintenance work on Blue Line metro corridorsDMRCSubscribersSubscribersUnder evaluation
DMRC invites bids for construction of 7 elevated stations on Lajpat Nagar-Saket G-Block Metro corridorDMRCSubscribersUnder evaluation
Delhi Metro: DMRC invites bids for Passenger Connection between Line 7 & Line 8 Extension at Azadpur Metro Station DMRCSubscribersSubscribersUnder evaluation
Delhi Metro: DMRC floats ₹1,373.36 Cr Tender for Civil Works on Rithala-Kundli CorridorDMRCSubscribersSubscribersUnder evaluation
Delhi Metro Set for AI-Powered CCTV Camera Upgrade: DMRC Floats ₹109 Cr TenderDMRCSubscribersUnder evaluation
Delhi Metro’s Rithala-Narela-Kundli Line Enters Construction Stage: Civil Tender Floated for 10 Stations & ViaductDMRCSubscribersUnder evaluation

Upcoming tenders

No upcoming tenders announced yet.

Bid values, closing dates and awardees are for subscribers. See plans.