Patna Metro nears completion of 7.8 km underground tunnelling on corridor II

2 min read
1
6,483
Patna Metro nears completion of 7.8 km underground tunnelling on corridor II
DMRC Floats Patna Metro Tender for Ballastless Track Installation on Corridor-1
Listen to this story
0:00

PATNA (Metro Rail News): Patna Metro has completed around 7.4 km of tunnelling on the 7.8-km underground section of Corridor II. It marks major progress on one of the project’s key stretches. Civil construction on the section is targeted for completion by October 2026. 

The underground stretch runs between the Malahi Pakri Ramp to Rajendra Nagar area and Akashvani. It will add six underground stations to the expanding Patna Metro network. 

Six underground stations on the upcoming stretch

The section that is 7.8 km in length will include:

Get the Daily Metro & Rail Brief

Join 125,000+ metro and rail professionals. Project updates, new tenders and contract awards from across India, in your inbox every day.

Free · One email a day · Unsubscribe anytime · We never share your address

  • Rajendra Nagar
  • Moin-ul-Haq Stadium
  • University
  • PMCH
  • Gandhi Maidan
  • Akashvani

Only around 400 metres of tunnelling work remains on the stretch. After completing the civil works, the project will move into the systems stage. This will include track laying, overhead electrical infrastructure, cabling and signalling works. Urban Development and Housing Minister Nitish Mishra said work was progressing across both the underground and elevated sections of the Patna Metro project.

Patna Metro’s Blue Line priority corridor already operational

Patna Metro has already started services on the 6.2-km priority corridor, which is a part of Corridor II. The corridor, known as the Blue Line, connects Patliputra Bus Terminus (ISBT) with Malahi Pakri. The operational section includes five stations:

SponsoredInnoBus Conference & Expo 2026, 23 December 2026, Bharat Mandapam, New Delhi
  • Patliputra Inter-State Bus Terminal
  • Zero Mile
  • Bhootnath
  • Khemnichak
  • Malahi Pakri

Khemnichak currently functions as a pass-through station. Authorities aim to open it for passenger use in November 2026. The complete Corridor II between Patna Junction and New ISBT spans around 14.5 km.

Elevated sections of Red Line also advance

Construction has also progressed on the elevated sections of Corridor I, or the Red Line.

Two stretches are nearing completion:

Section LengthStation 
Khemnichak-Mithapur3.1Jaganpura, Ramkrishna Nagar, Mithapur
Rukanpura-Danapur3.2Patliputra, RPS More, Saguna More, Danapur

The project has completed viaduct construction on both sections. Station construction and finishing work are now underway. Officials expect the Khemnichak-Mithapur section to open next year, further expanding Metro connectivity in the city.

Work begins on another major underground section

Meanwhile, construction has started on the 10.5-km underground section between Mithapur and Rukanpura along Nehru Path. The stretch will include six stations:

  • Patna Junction, an interchange station
  • Vidyut Bhawan
  • Vikas Bhawan
  • Patna Zoo
  • Raja Bazaar
  • Rukanpura

The project will eventually create a network combining elevated and underground corridors across key residential, commercial and institutional areas of Patna.

Also Read: 3 New Trains to Join Patna Metro Fleet by December 2026

fd7b5cf1 1e2e 4f4e 8260 6bdbbb258f91Read nextDMRC Floats Patna Metro Tender for Ballastless Track Installation on Corridor-114 Nov 2026

Add to Preferred Sources

1 COMMENT

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here