L&T Secures Package CA-234 of Mumbai Metro Line 4 

1
1727
Mumbai Metro Line 4
Mumbai Metro Line 4

Mumbai (Metro Rail News): Mumbai Metro progressed as Larsen & Toubro ( L&T) has been declared as the lowest Bidder by the Mumbai Metropolitan Region Development Authority ( MMRDA) for 5 major systems under Package CA-234 of Line 4 & Line 4A spanning 35.2 km connecting Wadala- Kasarvadavali – Gaimukh.

MMRDA re-invited Bids for this contract in February 2024 with an estimated cost of Rs.4279.49 crores and a 19-year contract duration. 

In November 2024, technical bids were opened to reveal that 2 firms had submitted bids for the contract. 

Contact Details

Under this contract, L&T will be responsible for supplying the major systems mentioned below: 

  •  Supplying rolling stock (39 trains (234 coaches) consisting of 6 coaches)
  •  CBTC signaling & train control (S&T)
  • Telecommunication System 
  • Platform screen doors (PSDs)
  • Depot machinery & plant (M&P) for Mogharpada Depot.

Note: L&T has partnered up with Alstom Transport for the rolling stock and signalling solution. 

Funding: Germany’s KfW will provide a loan of EUR 545 million for the design and construction phase, which will last 168 weeks (about 3.2 years). MMRDA will cover the maintenance for 17 years, including 2 years for handling defects.

MMRDA’s Brief Scope: Design, Manufacture, Supply, Installation, Integration, Testing and Commissioning of Rolling Stock, Communication Based Signaling & Train Control, Telecommunication, Platform Screen Doors Systems, and Depot Machinery & Plant including 15 Years of Comprehensive Maintenance After 2 Years of Defect Liability Maintenance Period of Line 4 and Extension Corridor (4A) [Wadala – Kasarvadavali – Gaimukh] of Mumbai Metro Rail Project of MMRDA.

As per the tender’s schedule, the 39 trainset has to be delivered according to the timeline mentioned below: 

Batch No.Number of TrainsDelivery Timeline (Weeks from Contract Signing)Delivery Timeline (Years & Months)
1st Batch1 Prototype TrainWeek 521 Year
2nd Batch9 TrainsWeek 701 Year 4 Months
3rd Batch10 TrainsWeek 881 Year 8 Months
4th Batch10 TrainsWeek 1042 Years
5th Batch9 TrainsWeek 1122 Years 2 Months

Further Information 

This development was recorded 3 years after Alstom Transport, the company that won the contracts for Line-4’s trains and signaling, withdrew from the project in 2022 because of slow progress in civil construction, particularly with the train depot, which still did not have a finalized location at that time.

1 COMMENT

  1. Thane Ghodhbunder residents have suffered the most in the last 20 years due to rapid urbanization, but the infrastructure building by the governments has not kept pace with it. Metro Line 6 would have reduced the burden from the roads and trains by almost 50 percent. But due to the never ending delay in completion of these projects is causing frustration among the residents. Even after paying Crores of Rupees for Apartments here, the ground reality is very bad. When will people get relief from these problems?

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.