L&T & J Kumar awarded Delhi Metro Phase IV tunneling contracts

0
1,702
L&T & J Kumar awarded Delhi Metro Phase IV tunneling contracts
Image for Representation.

DELHI (Metro Rail News): Larsen & Toubro and J Kumar Infraprojects on 9th March 2022, Wednesday were awarded 2 underground tunnelling contracts which are DC-09 & DC-08 of the 65.1 km Delhi Metro Phase 4 project‘s 23.622 km Silver Line.

Both of these firms had submitted the lowest revised bids in mid-February after the Delhi Metro Rail Corporation (DMRC) re-invited price bids from the technically qualified bidders of the original round.

Both packages are being financed by JICA through Rs. 8,390 crore ODA loan and have a 42-month deadline.

Package DC-08

This 6.116 km Aerocity – Kishangarh section is on the western end of the 23.622 km Silver Line and comprises 4 stations at Aerocity, Mahipalpur, Vasant Kunj and Kishangarh.

The weekly brief metro & rail professionals read.

One email a week. We never share your address. Unsubscribe anytime.

  • DMRC’s Estimate: Rs. 1349 crore
  • Awarded to: J Kumar Infraprojects (JKIL)
  • Final Contract Value: Rs. 1611.74 crore (INR 1426,99,50,000 + USD 2,45,00,000)

The scope of this project includes Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box and four Underground stations namely Aerocity, Mahipalpur, Vasant Kunj and Kishangarh with Entry/Exits & Connecting subways from chainage (-) 760 mt. to 5356.285 mt. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.

Package DC-09

This 6.51 km section, with twin-tunnels precisely in the middle of the Silver Line will connect Kishangarh Station’s east-end (chainage 5356.285) with a ramp (chainage 11867.000) west of Saket G Block Station through 4 stations at Chhattarpur (interchange with Yellow Line), Chhattarpur Mandir, IGNOU and Neb Sarai.

  • DMRC’s Estimate: Rs. 1428 crore
  • Awarded to: Larsen & Toubro (L&T)
  • Final Contract Value: Rs. 1737 crore (INR 1533,50,10,000 + USD 2,70,00,000)

The scope for this project includes Design and Construction of Twin Tunnel (Up & Down Line) by Shield TBM, Cut and Cover Tunnel box, Underground Ramp and four Underground stations namely Chhattarpur, Chhattarpur Mandir, IGNOU and Neb Sarai with Entry/Exits & Connecting subways from chainage 5356.285 meters to 11867.000 meters. of Aerocity to Tughlakabad Corridor of Phase-IV of Delhi MRTS.

Project Overview

Delhi Metro – Information, Route Map, Fares, Tenders & Updates

All corridors, status, routes and the latest news in one place →

Join the Discussion

Have a correction, an on-the-ground update, or a question about this project? Engineers, operators and consultants across the metro, rail and RRTS sector read these threads.

Every comment is read by our editorial team before it appears.

Please enter your comment!
Please enter your name here