NEW DELHI (Metro Rail News): The National Capital Region Transport Corporation (NCRTC) opened the bids for the civil construction package Package-1(DM/CN/COR-OF/058) and Package-2 (DM/CN/COR-OF/059).
L&T, which is an Indian multinational conglomerate company headquartered in Mumbai, emerged as the lowest bidder (L1) for the civil construction package Package-1 and Package-2 work.
For the construction work of package-1 elevated viaduct from Duhai (EPE) to start from North Modi Nagar and two elevated stations via Murad Nagar and Modi Nagar South (Excluding architectural finishing and pre-engineered steel roof structure of stations) of Delhi-Ghaziabad-Meerut RRTS corridor, there are four contractors participated i.e L&T, Afcons, NEC, JMC respectively.
Participants and Bidding Amount
Bidder Name | Quoted Amount | Rank |
---|---|---|
L&T | 784.00 Crore | L1 |
Afcons | 871.25 Crore | L2 |
NEC | 969.75 Crore | L3 |
JMC | 1035.05 Crore | L4 |
As well as for the construction work of Package-2 elevated viaduct from the start of Modi Nagar North station to Shatabdi Nagar station and elevated stations via Modi Nagar North, Meerut South, Partapur, Rithani & Shatabdi Nagar of Delhi-Ghaziabad-Meerut RRTS corridor, there are three contractors participated i.e L&T, Afcons, NEC respectively.
For the Package-1 construction, L&T quoted Rs 784 crore against the estimated value of contract Rs 860 crores and for the package-2 construction, L&T quoted Rs. 1013.95 crores against the estimated value of contract Rs 1096 crores.
Participants and Bidding Amount
Bidder Name | Quoted Amount | Rank |
---|---|---|
L&T | 1013.95 Crore | L1 |
Afcons | 1114.97 Crore | L2 |
NEC | 1235.45 Crore | L3 |
The total distance of Delhi-Ghaziabad-Meerut RRTS Corridor is 82 kilometres long. The construction work on the 17-kilometre first section of the Delhi-Ghaziabad-Meerut RRTS corridor is continuing on in full swing. Along with construction work of pillars has been underway between Sahibabad and Duhai. First girder (segment) for the viaduct of Delhi-Ghaziabad-Meerut RRTS Corridor has been cast at NCRTC’s casting yard located at Vasundhara, Ghaziabad. The viaducts will also be soon visible on the ground. The operation on the main section is proposed from March 2023. The main section has four stations which are Sahibabad, Ghaziabad, Guldhar and Duhai.
Madam L and T company me civil Ka koi job news hai kaya
I Er.and personal competition
Am I interested for job store ,IR and Account
Sent your resume to virenbkn@gmail.com
I am interest for job as a surveyor engineer
I’m Ramjan ali
Colifikesan B.A.
Fast tame suparwaijar
I am interested this project so that allready worked Delhi metro Project
I am civil engineer
Any contact details of project Manager “Delhi-Ghaziabad-Meerut RRTS”
I am interested job for electrical supervisor
Only meerut location
I am intrested for fabrication work
I am intrested for fabrication work only meerut location
I am intresed for fabrication work only meerut city. My qualification grauduat
I am intresed for mechanical work only
Live in mumbai metro line no 6 bco2r
Clients DMRC, MMRDA mumbai metro line
I am interested this project.
I am working as Sr execution Engineer in Bengalore metro rail corporation limited.
Project name- Metro Depot
I am working in psc casting yard as Foreman continues 20 year. have you any type of job
Iti ke h electrician se
N A K Group, Pune – Service Provider of Scissor Lifts and Boom Lift Man Lift
Service Provider of Scissor Lifts, Boom Lift Man Lift & Scissor Lift offered by N A K Group from Pune, Maharashtra, India.
8433030400
Goswami22796@gmail.com