GHAZIABAD (Metro Rail News): The first trainset of India’s first RRTS has reached Duhai Depot today. This trainset was loaded on a trailer from the manufacturing plant located in Savli, Gujarat and brought to Duhai via road.
In its journey to reach Duhai Depot, the train has travelled through three states, Rajasthan, Haryana and finally Uttar Pradesh. All the 6 coaches of the trainset were loaded on six separate trailers. On reaching the Duhai depot, they were unloaded with the help of a crane and in the coming days, the trainset will be assembled in the depot itself.
Tracks have already been completed for its arrival at the Duhai depot and preparations are going on for the testing. For the operation of RRTS trains, an administrative building has been built in the Duhai depot itself.
The 17 km long priority section has five stations, Sahibabad, Ghaziabad, Guldhar, Duhai and Duhai Depot. NCRTC is planning to commence the trial runs on the priority section by the end of this year and to make it operational for the public by 2023.
The interiors along with the commuter-centric features of India’s first RRTS trains were unveiled on March 16, 2022, at the Duhai Depot, Ghaziabad. These RRTS trains will be the fastest trains in India with a design speed of 180km/h, operational speed of 160km/h and an average speed of 100 km /h.